Overview
ELYSIAN TOWER
ELYSIAN GROUP · Ludhiana
Units26
Completion2028-12-31Proposed
Valid to2028-12-31
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 11 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 49 documents · 23 source links |
Registration
Registration
| Promoter | ELYSIAN GROUP | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PC0199 | |
| Valid to | 2028-12-31 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | 2023-03-09 | |
| License as Promoter from competent Authority | 2022-08-01 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2022-11-15 | |
| NOC from Mining Department | 2023-01-19 | |
| NOC from NHAI/ PWD | Permissions (Received) | 2022-11-10 |
| Other Document (NOC Drainage) | 2023-04-05 | |
| Other Document (NOC Drainage) | 2023-07-05 | |
| Other Document (NOC Forest along with Order) | 2023-11-17 | |
| Other Document (NOC of Solid Waste, Environmental Clearance, AAI) | 2024-02-07 | |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2023-02-06 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹12,60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,063.027 | |
|---|---|---|
| Towers | 11 | |
| Maximum floors | 10 | |
| Units | 26 |
Unit types
| COMMERCIAL SCO | 104.047 | 10 | COMMERCIAL SCO 13 TO 22 |
| COMMERCIAL SCO | 418.289 | 1 | COMMERCIAL SCO 12 |
| COMMERCIAL SCO | 100.335 | 5 | COMMERCIAL SCO 7 TO 11 |
| COMMERCIAL SCO | 111.865 | 3 | COMMERCIAL SCO 4 TO 6 |
| COMMERCIAL SCO | 104.407 | 1 | COMMERCIAL SCO 25 |
| COMMERCIAL SCO | 126.05 | 1 | COMMERCIAL SCO 2 |
| COMMERCIAL SCO | 168.931 | 1 | COMMERCIAL SCO 3 |
| COMMERCIAL SCO | 104.632 | 1 | COMMERCIAL SCO 26 |
| COMMERCIAL SCO | 104.256 | 1 | COMMERCIAL SCO 24 |
| COMMERCIAL SCO | 104.122 | 1 | COMMERCIAL SCO 23 |
| COMMERCIAL SCO | 96.388 | 1 | COMMERCIAL SCO 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-01-01 | |
|---|---|---|
| Proposed completion | 2028-12-31 |
Quarterly progress
| 2024-Q2 | 2024-11-17 |
| 2024-Q3 | 2024-11-17 |
| 2024-Q4 | 2025-02-21 |
| 2025-Q1 | 2025-06-30 |
| 2025-Q2 | 2025-09-24 |
| 2025-Q3 | 2025-12-08 |
| 2025-Q4 | 2026-02-08 |
| 2026-Q1 | 2026-07-06 |
| 2026-Q2 | 2026-09-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ELYSIAN GROUP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Central Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11634&inPromoter_ID=2513&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2023-03-09
- License as Promoter from competent Authority · 2022-08-01
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-11-15
- NOC from Mining Department · 2023-01-19
- NOC from NHAI/ PWD · 2022-11-10
- Other Document (Drawing of Ground Water) · 2023-03-31
- Other Document (NOC Drainage) · 2023-04-05
- Other Document (NOC Drainage) · 2023-07-05
- Other Document (NOC Forest along with Order) · 2023-11-17
- Other Document (NOC of Solid Waste, Environmental Clearance, AAI) · 2024-02-07
- Pollution Clearance from Punjab Pollution Control Board · 2023-02-06
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2023-03-09
- License as Promoter from competent Authority · 2022-08-01
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-11-15
- NOC from Mining Department · 2023-01-19
- NOC from NHAI/ PWD · 2022-11-10
- Other Document (NOC Drainage) · 2023-04-05
- Other Document (NOC Drainage) · 2023-07-05
- Other Document (NOC Forest along with Order) · 2023-11-17
- Other Document (NOC of Solid Waste, Environmental Clearance, AAI) · 2024-02-07
- Pollution Clearance from Punjab Pollution Control Board · 2023-02-06
- 2024-Q2 · 2024-11-17
- 2024-Q3 · 2024-11-17
- 2024-Q4 · 2025-02-21
- 2025-Q1 · 2025-06-30
- 2025-Q2 · 2025-09-24
- 2025-Q3 · 2025-12-08
- 2025-Q4 · 2026-02-08
- 2026-Q1 · 2026-07-06
- 2026-Q2 · 2026-09-11