Overview
EMAAR BUSINESS DISTRICT 75A
EMAAR INDIA LIMITED · Gurugram
Units55
Completion2027-08-23Proposed
Registered on2023-02-02
Valid to2027-08-23
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 11 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 50 documents · 2 source links |
Registration
Registration
| Promoter | EMAAR INDIA LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/690/422/2023/34 DATED 02.02.2023 | |
| Registered on | 2023-02-02 | |
| Valid to | 2027-08-23 | |
| Status (as filed) | Registered | |
| Proposed completion | 2027-08-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 129 of 2022 | Town & Country Planning Department | |
| Layout Plan | 2022-08-25 | ||
| Building Plan | 2022-08-25 | ||
| I. LOI VIDE MEMO NO. LC-4755-JE(VA)/2022/19299 | 2022-07-07 | ||
| II. LICENSE APPROVED VIDE MEMO NO. 129 OF 2022 | 2022-08-24 | ||
| III. APPROVED LAYOUT VIDE DRAWING NO. DTCP 8566 | 2022-08-25 | ||
| IV. ASSURANCE OF STORM WATER CONNECTION | 2022-08-29 | ||
| V. ASSURANCE OF SEWERAGE CONNECTION | 2022-08-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹17,54,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹81,43,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1.5 | |
|---|---|---|
| Units | 55 |
Unit types
| Plot | 1 | |
| Plot | 8 | |
| Plot | 1 | |
| Plot | 13 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 13 | |
| Plot | 2 | |
| Plot | 2 | |
| Plot | 13 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-09-24 | |
|---|---|---|
| Proposed completion | 2027-08-23 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | EMAAR INDIA LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | AXIS BANK | |
| Other projects in this city pack | 19 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2073
- Registration Certificate · 2023-02-02
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2022-08-26 · Sign in to download
- LOI · 2022-08-26 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2022-08-30
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2022-08-30 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2022-08-30
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2022-08-30 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2022-08-30
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2022-08-30 · Sign in to download
- DEMARCATION PLAN · 2022-08-31
- DEMARCATION SUPERIMPOSED ON LAYOUT · 2022-08-31 · Sign in to download
- ASSURANCE APPROVAL OF STORM WATER AND SEWERAGE · 2022-08-31
- BBA DRAFT · 2022-08-31 · Sign in to download
- STANDARD PLAN SUBMISSION-D2 · 2023-06-15
- STANDARD PLAN SUBMISSION-B09 & B11 · 2023-06-15
- SIJRA & REVENUE DOCS (EBD-75A) · 2023-06-15 · Sign in to download
- DRAINAGE SCHEME · 2023-06-15 · Sign in to download
- FLUSHING SCHEME · 2023-06-15 · Sign in to download
- ROAD SCHEME · 2023-06-15 · Sign in to download
- SERVICE ESTIMATE REPORT · 2023-06-15 · Sign in to download
- SEWERAGE SCHEME · 2023-06-15 · Sign in to download
- WATER SUPPLY SCHEME · 2023-06-15 · Sign in to download
- STANDARD PLAN SUBMISSION-A1 · 2023-06-15
- STANDARD PLAN SUBMISSION-A2,A8,D7,D11 · 2023-06-15
- STANDARD PLAN SUBMISSION-A3,A5,A9 · 2023-06-15
- STANDARD PLAN SUBMISSION-C01 · 2023-06-15
- STANDARD PLAN SUBMISSION-A4,A6 · 2023-06-15
- STANDARD PLAN SUBMISSION-A7,D6,D12,D16 · 2023-06-15
- STANDARD PLAN SUBMISSION-A10 · 2023-06-15
- STANDARD PLAN SUBMISSION-B01 & C12A · 2023-06-15
- STANDARD PLAN SUBMISSION-B02, B08, B12,C02,C04,C06,C08,C12 · 2023-06-15
- STANDARD PLAN SUBMISSION-B03, B05, C03,C5,C9,C11 · 2023-06-15
- STANDARD PLAN SUBMISSION-B04, B06 & C10 · 2023-06-15
- STANDARD PLAN SUBMISSION-B07, B12A & C07 · 2023-06-15
- STANDARD PLAN SUBMISSION-B10 · 2023-06-15
- STANDARD PLAN SUBMISSION-B14 · 2023-06-15
- STANDARD PLAN SUBMISSION-B15 · 2023-06-15
- STANDARD PLAN SUBMISSION-D1 · 2023-06-15
- STANDARD PLAN SUBMISSION-D8,D10,D14 · 2023-06-15
- LAND TITLE SEARCH REPORT · 2023-06-15 · Sign in to download
- STANDARD PLAN SUBMISSION-D3 · 2023-06-15
- STANDARD PLAN SUBMISSION-D4 · 2023-06-15
- STANDARD PLAN SUBMISSION-D5,D9,D12A,D15 · 2023-06-15
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2023-06-15 · Sign in to download
- STANDARD PLAN SUBMISSION-D17 · 2023-06-15
- COLLABORATION AGREEMENT-AMAR GYAN DEVELOPMENTS - UP TO 31.12.2009 · 2023-06-15 · Sign in to download
- COLLABORATION AGREEMENT-SNOW WHITE BUILDCON __REGD. ON 10.06.13 · 2023-06-15 · Sign in to download
- SUPPLEMENTARY COLLABORATION AGREEMENT_75A · 2023-06-15 · Sign in to download
- NEC- 4.56 (EBD-75A) · 2023-06-15 · Sign in to download
- CC uploaded · 2025-01-24 · Sign in to download