Overview
Emerald Court Phase II (Apex & Ceyane) - Demolished as per the order of Hon'ble Superme Court
SUPERTECH LIMITED · Gautam Buddha Nagar
Completion2021-11-30Revised · Proposed 2021-06-01
Registered on2017-08-15
Valid to2021-11-30
Approvals1
Complaints3As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 3 project complaints · 2,803 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 1 site detail |
| Construction & progress | 3 progress details · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 4 documents · 10 source links |
Registration
Registration
| Promoter | SUPERTECH LIMITED | |
|---|---|---|
| District | Gautam Buddha Nagar | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ11486 | |
| Registered on | 2017-08-15 | |
| Valid to | 2021-11-30 | |
| Project type | Residential | |
| Status (as filed) | NCLT PROJECTS | |
| Proposed completion | 2021-06-01 | |
| Revised completion | 2021-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date |
|---|---|---|
| Permit | 09/TPA /III/142 | 2009-11-26 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 3 | |
|---|---|---|
| Promoter | 2,803 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹56,60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,557 |
|---|
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2009-12-01 | |
|---|---|---|
| Proposed completion | 2021-06-01 | |
| Revised completion | 2021-11-30 |
Extensions
| Valid to | Reason |
|---|---|
| 2021-11-30 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SUPERTECH LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | PUNJAB & SIND BANK | |
| Other projects in this city pack | 28 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Modarch pvt. Ltd |
| Engineer | Optimum Design Pvt Ltd |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=5Yq0dGJ1am4=&hfFlag=9emr4VdBw22M7BGjKtJWMPDI4s5cHQZP&NPJ6RAme=LtWee0jZCkxMcXV5X8vroRYHPBnXS1/d881LNUTTbswDIgf6wFNOeg==&PaURJEMAN4=ZL9MNERkNdbSz55zhUco6w==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/WebService1.asmx/loadNCLTprojectWithParameter
- https://up-rera.in/WebService1.asmx/loadPlot_new
- https://up-rera.in/WebService1.asmx/loadVillasnew
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GAUTAM%20BUDDHA%20NAGAR
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=5Yq0dGJ1am4=
- View Order · Sign in to download
- Sanctioned Building/ Block Plan (Add Plans for All Buildings or Blocks) · 2018-01-18
- Sanctioned Building/ Block Plan (Add Plans for All Buildings or Blocks) · 2018-01-18
- Sanctioned Building/ Block Plan (Add Plans for All Buildings or Blocks) · 2018-01-18