Overview
EMERALD ESTATE
EMAAR MGF LAND LIMITED · Gurugram
Completion2022-08-23Revised · Proposed 2022-08-23
Registered on2017-08-24
Valid to2022-08-23
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 16 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 30 documents · 3 source links |
Registration
Registration
| Promoter | EMAAR MGF LAND LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 104 OF 2017 DATED 24.08.2017 | |
| Registered on | 2017-08-24 | |
| Valid to | 2022-08-23 | |
| Status (as filed) | Registered | |
| Proposed completion | 2022-08-23 | |
| Revised completion | 2022-08-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 06 of 2008 | Town & Country Planning Department | |
| Layout Plan | 2009-12-29 | ||
| Building Plan | 2009-12-29 | ||
| I. LICENSE APPROVAL | 2008-01-17 | ||
| II. LOI | 2007-12-14 | ||
| III. LC-IV | 2008-01-17 | ||
| IV. AIRPORT HEIGHT CLEARANCE | 2010-01-14 | ||
| V. FIRE SCHEME APPROVAL | 2015-03-26 | ||
| VI. SERVICE PLAN ESTIMATES | 2016-10-14 | ||
| VII. BUILDING PLAN | 2009-12-29 | ||
| VIII. ENVIRONMENT CLEARANCE | 2010-07-20 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹17,68,00,000 | |
|---|---|---|
| Construction | ₹2,40,20,00,000 | |
| Total | ₹3,82,17,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 175 |
|---|
Unit types
| Type |
|---|
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
| 11 |
| 12 |
| 13 |
| 14 |
| 15 |
| 16 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2010-07-31 | |
|---|---|---|
| Proposed completion | 2022-08-23 | |
| Revised completion | 2022-08-23 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | EMAAR MGF LAND LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 9 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1047
- https://nominatim.openstreetmap.org/search?q=sector+65%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-08-24
- LICENSE · 2020-03-12
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-03-12 · Sign in to download
- BR-III · 2020-03-12 · Sign in to download
- SERVICE PLAN ESTIMATE APPROVAL GH 25.499 ACRES · 2020-03-12
- ARAVALLI NOC- EMERALD ESTATE · 2020-03-12
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-03-12 · Sign in to download
- ZONING PLAN · 2020-03-12
- LC-IV & LV-A. 25.499 ACRES · 2020-03-12 · Sign in to download
- LOI 25.499 · 2020-03-12 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2020-03-12 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2020-03-12
- AIRPORT HEIGHT CLEARANCE · 2020-03-12
- ENVIRONMENTAL CLEARANCE · 2020-03-12
- LAYOUT PLAN · 2020-03-12
- NON ENCUMBRANCE CERTIFICATE · 2020-03-12 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2020-03-12
- APPROVAL OF FIRE FIGHTING SCHEME · 2020-03-12
- BBA AND ALLOTTMENT LETTER · 2020-03-12 · Sign in to download
- REP-II · 2020-03-12 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-02-01
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-02-04
- ANNUAL REPORT 2016-17 · 2020-02-04 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-02-04
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2020-02-04 · Sign in to download
- ANNUAL REPORT 2018-19 · 2020-02-04 · Sign in to download
- ANNUAL REPORT 2017-18 · 2020-02-04 · Sign in to download
- OC uploaded · 2023-08-24 · Sign in to download
- OC uploaded · 2023-08-24 · Sign in to download
- CC uploaded · 2026-05-13 · Sign in to download