Overview
ENIGMA, PHASE-1A
ATHENA INFRASTRUCTURE LIMITED · Gurugram
Units0
Completion2018-03-31Revised · Proposed 2018-03-31
Registered on2017-11-20
Valid to2018-03-31
Approvals10
Cases6
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Disputes & cases | 6 cases |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 9 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 35 documents · 4 source links |
Registration
Registration
| Promoter | ATHENA INFRASTRUCTURE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 353 OF 2017 DATED 20.11.2017 | |
| Registered on | 2017-11-20 | |
| Valid to | 2018-03-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2018-03-31 | |
| Revised completion | 2018-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 213 of 2007 dated 5.09.2007 10 of 2011 dated 29.01.2011 64 of 2012 dated 20.06.2012 | Town & Country Planning Department | |
| Layout Plan | 2013-08-23 | ||
| Building Plan | 2013-08-23 | ||
| I. ENVIRONMENT CLEARANCE APPROVAL | 2013-06-26 | ||
| II. AIRPORT HEIGHT CLEARANCE | 2017-09-06 | ||
| III. FIRE SCHEME APPROVAL | 2014-03-31 | ||
| IV. SERVICE PLAN ESTIMATES APPROVAL | 2015-05-18 | ||
| V. LICENSE APPROVAL | 2012-06-20 | ||
| VI. ZONING PLAN APPROVAL | 2012-06-21 | ||
| VII. BUILDING PLAN / SITE PLAN APPROVAL | 2013-08-23 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA-GRG-3018-2022 | HRERA Gurugram | |
| RERA-GRG-5302-2019 | HRERA Gurugram | Pending |
| RERA-GRG-3803-2022 | HRERA Gurugram | Pending |
| RERA-GRG-3801-2022 | HRERA Gurugram | Pending |
| RERA-GRG-3522-2022 | HRERA Gurugram | Pending |
| RERA-GRG-5085-2022 | HRERA Gurugram | Pending |
Complaints & cases
| Cases | 6 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹30,83,00,000 | |
|---|---|---|
| Construction | ₹1,07,01,00,000 | |
| Total | ₹2,00,83,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1.75 | |
|---|---|---|
| Units | 0 |
Unit types
| 1 | 0 |
| 2 | 0 |
| 3 | 0 |
| 4 | 0 |
| 5 | 0 |
| 6 | 0 |
| 7 | 0 |
| 8 | 0 |
| 9 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-11-17 | |
|---|---|---|
| Proposed completion | 2018-03-31 | |
| Revised completion | 2018-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ATHENA INFRASTRUCTURE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/MzUzIG9mIDIwMTcgREFURUQgMjAuMTEuMjAxNw==
- https://haryanarera.gov.in/view_project/project_preview_open/1160
- https://nominatim.openstreetmap.org/search?q=sector+110%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-11-20
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-12-30 · Sign in to download
- UPPER BASEMENT PART-1 · 2019-12-30 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-12-30
- TOWER F, H J TYPICAL FLOOR PLAN 2 · 2019-12-30
- TOWER E, G, I SECTION · 2019-12-30 · Sign in to download
- TOWER A UPPER FLOOR DUPLEXES · 2019-12-30 · Sign in to download
- ROAD AND FIRE FIGHTING · 2019-12-30 · Sign in to download
- LOWER BASEMENT PART-2 · 2019-12-30 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-12-30
- TOWER E, G, I TYPICAL FLOOR PLAN · 2019-12-30
- TOWER F,H,J SECTION · 2019-12-30 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-12-30
- TOWER A DUPLEXES · 2019-12-30 · Sign in to download
- TOWER A TO D TYPICAL FLOOR PLAN · 2019-12-30
- TOWER F,H,J ELEVATION · 2019-12-30 · Sign in to download
- TOWER F, H J TYPICAL FLOOR PLAN · 2019-12-30
- WATER SUPPLY · 2019-12-30 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-12-30 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-12-30
- ELECTRICAL SUPPLY SCHEME · 2019-12-30 · Sign in to download
- ZONING PLAN · 2019-12-30
- TOWER E,G,I ELEVATIONS · 2019-12-30 · Sign in to download
- STROM WATER DRAINAGE · 2019-12-30 · Sign in to download
- EXTERNAL STREET LIGHTING · 2019-12-30 · Sign in to download
- DEMARCATION PLAN · 2019-12-30
- LOWER BASEMENT PART-1 · 2019-12-30 · Sign in to download
- TOWER A TO D TYPICAL FLOOR PLAN 2 · 2019-12-30
- TOWER E, G, I TYPICAL FLOOR PLAN 2 · 2019-12-30
- TOWER E,G,I ELEVATIONS 2 · 2019-12-30 · Sign in to download
- TOWER A TO D TYPICAL FLOOR PLAN · 2019-12-30
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-12-30 · Sign in to download
- UPPER BASEMENT PART-2 · 2019-12-30 · Sign in to download
- OC uploaded for tower A, E,F and EWS block etc · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download