Overview
ESPIRE TOWERS (TOWER-A)
ESPIRE INFRASTRUCTURE CORPORATION LTD · Faridabad
Completion2021-12-31Revised
Valid to2023-09-30
Approvals8
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 1 progress detail |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 9 documents · 4 source links |
Registration
Registration
| Promoter | ESPIRE INFRASTRUCTURE CORPORATION LTD | |
|---|---|---|
| District | Faridabad | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-FBD-109-2019 | |
| Valid to | 2023-09-30 | |
| Status (as filed) | Registered | |
| Revised completion | 2021-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No. 205 of 2007 dated 03.08.2007. License Valid upto 02.08.2019. | Town & Country Planning Department | |
| Layout Plan | 2015-08-07 | ||
| Building Plan | 2015-08-07 | ||
| I. LICENSE NO. 205 OF 2007 | 2007-08-14 | ||
| II. RENEWAL OF LICENSE NO. 205 OF 2007 | 2018-11-14 | ||
| III. OCCUPATION CERTIFICATE FOR TOWER-C, D AND EWS. | 2015-10-28 | ||
| IV. APPROVAL OF BUILDING PLANS | 2015-08-07 | ||
| V. OCCUPATION CERTIFICATE FOR TOWER-B. | 2017-07-14 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1926-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹14,37,00,000 | |
|---|---|---|
| Construction | ₹10,99,17,000 | |
| Total | ₹30,08,41,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,509.69 | |
|---|---|---|
| FAR | 1.75 |
Unit types
| Type |
|---|
| 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Revised completion | 2021-12-31 |
|---|
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ESPIRE INFRASTRUCTURE CORPORATION LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLUZCRC0xMDktMjAxOQ==
- https://haryanarera.gov.in/view_project/project_preview_open/457
- https://nominatim.openstreetmap.org/search?q=sector+37%2C+Faridabad%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-03-11 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-03-09
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-03-09
- ZONING PLAN · 2019-03-09
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-03-09
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-03-09 · Sign in to download
- EXTENSION/RC UPLOAD · 2024-03-12 · Sign in to download
- Occupation Certificate Uploaded · 2024-03-12 · Sign in to download