Overview
Factory Outlets
BURJ DOWNTOWN PRIVATE LIMITED · Moga
Units79
Completion2028-11-07Proposed
Valid to2028-11-07
Approvals14
Sections
| Property title & search report | |
|---|---|
| Approvals | 14 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 36 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 38 documents · 22 source links |
Registration
Registration
| Promoter | BURJ DOWNTOWN PRIVATE LIMITED | |
|---|---|---|
| District | Moga | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-MGA52-PC0347 | |
| Valid to | 2028-11-07 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-11-07 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2025-03-31 |
| CLU Certificate | ||
| Electric Substation NOC | 2024-03-11 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2025-03-31 |
| License as Promoter from competent Authority | 2022-05-25 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2023-03-10 | |
| NOC from Mining Department | 2023-07-31 | |
| NOC from NHAI/ PWD | 2022-08-01 | |
| Other Document (FOREST NOC STG 1) | 2023-09-18 | |
| Other Document (FOREST NOC) | 2025-05-14 | |
| Other Document (FOREST NOC) | 2023-09-18 | |
| Pollution Clearance from Punjab Pollution Control Board | 2023-04-26 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-01-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹22,60,50,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 36,385.28 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 79 | |
| Units | 79 |
Unit types
| FOOD COURT | 1,272.76 | 1 | BURJ DOWN TOWN-1 |
| DRIVE THRU - 1 | 390.88 | 1 | BURJ DOWN TOWN-1 |
| DRIVE THRU- 2 | 262.45 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 1 | 272.28 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 2-19 | 265.95 | 18 | BURJ DOWN TOWN-1 |
| SHOP no. 20 | 283.81 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 21 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 22 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 23 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 24 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 25 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 26 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 27 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 28 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 29 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 30 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 31 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 32 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 33 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 34 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 35 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 36 | 274.75 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 37 | 137.38 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 38 | 137.38 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 39 | 137.38 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 40 and 53 | 202.05 | 2 | BURJ DOWN TOWN-1 |
| SHOP no. 41 to 52 | 151.9 | 12 | BURJ DOWN TOWN-1 |
| SHOP no. 54 to 66 | 134.94 | 13 | BURJ DOWN TOWN-1 |
| SHOP no. 67 | 373.93 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 68 to 70 | 273.13 | 3 | BURJ DOWN TOWN-1 |
| SHOP no. 71 | 273.13 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 72 | 269.88 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 73 | 269.88 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 74 | 269.88 | 1 | BURJ DOWN TOWN-1 |
| SCO no. 75 | 269.88 | 1 | BURJ DOWN TOWN-1 |
| SHOP no. 76 | 276.39 | 1 | BURJ DOWN TOWN-1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-11-08 | |
|---|---|---|
| Proposed completion | 2028-11-07 |
Quarterly progress
| 2025-Q2 | 2026-08-06 |
| 2025-Q3 | 2026-08-06 |
| 2025-Q4 | 2026-08-06 |
| 2026-Q1 | 2026-08-06 |
| 2026-Q2 | 2026-08-06 |
| 2026-Q3 | 2026-10-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BURJ DOWNTOWN PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11833&inPromoter_ID=2713&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-03-31
- Borewell Registration certificate from Central Ground Water Authority · 2025-02-20
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-03-11
- Environment Clearance certificate/ NOC · 2025-03-31
- License as Promoter from competent Authority · 2022-05-25
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-03-10
- NOC from Mining Department · 2023-07-31
- NOC from NHAI/ PWD · 2022-08-01
- Other Document (FOREST NOC STG 1) · 2023-09-18
- Other Document (FOREST NOC) · 2025-05-14
- Other Document (FOREST NOC) · 2023-09-18
- Pollution Clearance from Punjab Pollution Control Board · 2023-04-26
- Pollution Clearance from Punjab Pollution Control Board · 2025-01-30
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-03-31
- CLU Certificate
- Electric Substation NOC · 2024-03-11
- Environment Clearance certificate/ NOC · 2025-03-31
- License as Promoter from competent Authority · 2022-05-25
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-03-10
- NOC from Mining Department · 2023-07-31
- NOC from NHAI/ PWD · 2022-08-01
- Other Document (FOREST NOC STG 1) · 2023-09-18
- Other Document (FOREST NOC) · 2025-05-14
- Other Document (FOREST NOC) · 2023-09-18
- Pollution Clearance from Punjab Pollution Control Board · 2023-04-26
- Pollution Clearance from Punjab Pollution Control Board · 2025-01-30
- 2025-Q2 · 2026-08-06
- 2025-Q3 · 2026-08-06
- 2025-Q4 · 2026-08-06
- 2026-Q1 · 2026-08-06
- 2026-Q2 · 2026-08-06
- 2026-Q3 · 2026-10-13