DOSLChhattisgarh Workspace

Overview

FM DREAM

M/S FIRSTMAN DEVELOPERS · BILASPUR
Construction progress60%As of 2024-12-31
Completion2027-03-11Revised · Proposed 2026-11-11
Registered on2022-03-29
Approvals4

Sections

Property title & search report
Approvals4 approvals
Contract & costs2 cost heads · 11 quarters
Technical report
Site & area596 unit types
Construction & progress4 progress details · 11 quarters
Developer & finance
Developer3 developer details
The evidence
Sources77 documents · 7 source links

Registration

Registration

PromoterM/S FIRSTMAN DEVELOPERS
DistrictBILASPUR
RegulatorCG RERA
Registration numberPCGRERA290322001373
Registered on2022-03-29
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2026-11-11
Revised completion2027-03-11