Overview
FORUS AZALEA
FORUS INITIATIVES · CHEMBUKAVU
Units16
Booked14 of 16
Construction progress100%As of 2023-06-23
Completion2023-05-01Revised · Proposed 2023-05-01
Registered on2021-05-24
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 4 unit types |
| Construction & progress | 5 progress details · 8 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 5 documents · 5 source links |
Registration
Registration
| Promoter | FORUS INITIATIVES | |
|---|---|---|
| District | Thrissur | |
| Locality | CHEMBUKAVU | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/010/2020 | |
| Registered on | 2021-05-24 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2023-05-01 | |
| Revised completion | 2023-05-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | DW4/BA/612/15-16 | 2016-11-15 | 2022-11-13 | THRISSUR MUNICIPAL CORPORATION |
| Development Permit | DW4/BA/612/15-16 | 2018-04-03 | 2022-11-13 | THRISSUR CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 764 | |
|---|---|---|
| Built-up (m²) | 3,258.43 | |
| Towers | 0 | |
| Units | 16 | |
| Booked | 14 |
Unit types
| 3BHK | 2 | 2 | FORUS AZALEA |
| 3BHK | 2 | 2 | FORUS AZALEA |
| 3BHK | 6 | 6 | FORUS AZALEA |
| 3BHK | 6 | 4 | FORUS AZALEA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-06-23 | |
| Start | 1900-01-01 | |
| Proposed completion | 2023-05-01 | |
| Revised completion | 2023-05-01 |
Quarterly progress
| Quarter |
|---|
| 2022-2023 Q2 |
| 2022-2023 Q3 |
| 2021-2022 Q1 |
| 2021-2022 Q3 |
| 2020-2021 Q4 |
| 2022-2023 Q4 |
| 2021-2022 Q4 |
| 2021-2022 Q2 |
Extensions
| Valid to |
|---|
| 2023-05-01 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | FORUS INITIATIVES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AXIS BANK | |
| Other projects in this city pack | 7 |
Professional firms
| Role | Firm |
|---|---|
| Architect | JIBU AND THOMAS ARCHITECTS |
| Engineer | STRUCTURAL SOLUTIONS |
| CA | MOHANDAS AND ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/48
- https://rera.kerala.gov.in/projects?district=594&page=4
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=XQJlflcqTFlN9En%2FaQemcWK33kxnX9EhLGBIs1UUCmnO%2F6ycliZWZ2Y17dzMek%2FtBPdSOEBHrWZClHkXROyp158vhtCsa%2BTRqF24CFPN3JmFtj7cW7EnqHviKQmKqZBH5mh6sQ%2Bsa6a9rLP8lDeS9QbxfRUeT3nJhRhZ%2Fv8VXcI%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=48&Division=1&UserID=30142&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Extension Certificate · Sign in to download
- Signed project certificate · 2021-05-24
- Extension certificate · 2022-07-02 · Sign in to download