Overview
G.K.s Burj Street
G.K.HOUSING &DEVELOPERS PRIVATE LIMITED · Ludhiana
Units83
Completion2029-09-11Proposed
Valid to2029-09-11
Approvals14
Sections
| Property title & search report | |
|---|---|
| Approvals | 14 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 13 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 23 source links |
Registration
Registration
| Promoter | G.K.HOUSING &DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PC0304 | |
| Valid to | 2029-09-11 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-09-11 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2025-03-10 |
| CLU Certificate | ||
| Electric Substation NOC | 2024-05-02 | |
| Electric Substation NOC | 2025-01-29 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2025-03-10 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2024-10-22 | |
| NOC from Mining Department | 2024-05-09 | |
| Other Document (AFFIDAVIT FOR NOC SUBMMIT IN SIX MONTH) | Legal Documents (To Be Applied) | 2024-10-25 |
| Other Document (Forest NOC) | 2024-11-13 | |
| Other Document (NOC PSTCL) | Clearances (Received) | 2024-09-25 |
| Other Document (PWD NOC FOR ROADS) | 2023-11-07 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-07-24 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-07-24 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹7,65,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 12,553.98 | |
|---|---|---|
| Units | 83 |
Unit types
| COMMERCIAL PLOT NO.01 | 259.15 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO.02TO30 | 3,112.91 | 29 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOTS NO.66TO69 | 159.79 | 4 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOTS NO. 72TO75 | 83.61 | 4 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOTS NO. 78TO83 | 125.41 | 6 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO.65 | 31.06 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO.70 | 62.36 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO.71 | 20.16 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO. 76 | 20.14 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO.77 | 32.7 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO. 84 | 32.7 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOT NO.31 | 97 | 1 | COMMERCIAL SCO PLOTS |
| COMMERCIAL PLOTS 33TO64 | 891.86 | 32 | COMMERCIAL SCO PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-09-12 | |
|---|---|---|
| Proposed completion | 2029-09-11 |
Quarterly progress
| 2025-Q2 | 2026-07-29 |
| 2025-Q3 | 2026-07-29 |
| 2025-Q4 | 2026-07-29 |
| 2026-Q1 | 2026-07-29 |
| 2026-Q2 | 2026-07-29 |
| 2026-Q3 | 2026-10-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | G.K.HOUSING &DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12168&inPromoter_ID=3064&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-03-10
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-05-02
- Electric Substation NOC · 2025-01-29
- Environment Clearance certificate/ NOC · 2025-03-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-10-22
- NOC from Mining Department · 2024-05-09
- Other Document (Forest NOC) · 2024-11-13
- Other Document (NOC PSTCL) · 2024-09-25
- Other Document (PWD NOC FOR ROADS) · 2023-11-07
- Pollution Clearance from Punjab Pollution Control Board · 2024-07-24
- Pollution Clearance from Punjab Pollution Control Board · 2024-07-24
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-03-10
- CLU Certificate
- Electric Substation NOC · 2024-05-02
- Electric Substation NOC · 2025-01-29
- Environment Clearance certificate/ NOC · 2025-03-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-10-22
- NOC from Mining Department · 2024-05-09
- Other Document (AFFIDAVIT FOR NOC SUBMMIT IN SIX MONTH) · 2024-10-25
- Other Document (Forest NOC) · 2024-11-13
- Other Document (NOC PSTCL) · 2024-09-25
- Other Document (PWD NOC FOR ROADS) · 2023-11-07
- Pollution Clearance from Punjab Pollution Control Board · 2024-07-24
- Pollution Clearance from Punjab Pollution Control Board · 2024-07-24
- 2025-Q2 · 2026-07-29
- 2025-Q3 · 2026-07-29
- 2025-Q4 · 2026-07-29
- 2026-Q1 · 2026-07-29
- 2026-Q2 · 2026-07-29
- 2026-Q3 · 2026-10-14