DOSLKarnataka Workspace

Overview

GAJABARWADI PHASE A

ALTAF ABDULHAMID ATTAR · Belagavi
Construction progress61%
Completion2026-12-31Proposed
Registered on2023-12-08
Valid to2026-12-31
Approvals10
Complaints0

Sections

Property title & search report
Approvals10 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads · 4 quarters
Technical report
Construction & progress3 progress details · 4 quarters
Developer & finance
Developer4 developer details
The evidence
Sources141 documents · 13 source links

Registration

Registration

PromoterALTAF ABDULHAMID ATTAR
DistrictBelagavi
RegulatorK-RERA
Registration numberPRM/KA/RERA/1249/369/PR/081223/006463
Registered on2023-12-08
Valid to2026-12-31
Project typePlotted Development
Status (as filed)APPROVED
Proposed completion2026-12-31