Overview
GALAXY TOWERS
AMARSONS AND ASSOCiATES · Sahibzada Ajit Singh Nagar (Mohali)
Units91
Completion2028-03-30Proposed
Valid to2028-03-30
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 4 unit types |
| Construction & progress | 2 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 30 documents · 27 source links |
Registration
Registration
| Promoter | AMARSONS AND ASSOCiATES | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0867 | |
| Valid to | 2028-03-30 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-03-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2022-04-22 |
| CLU Certificate | |
| Defense Clearance | 2022-04-22 |
| Electric Substation NOC | 2023-06-16 |
| License as Promoter from competent Authority | 2022-05-11 |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2022-04-18 |
| NOC from Mining Department | 2023-02-07 |
| Other Document (NOC for Forest Drainage National Highway) | 2023-08-03 |
| Other Document (NOC from MC regarding Sewage treatment) | 2022-06-29 |
| Pollution Clearance from Punjab Pollution Control Board | 2023-09-07 |
| Pollution Clearance from Punjab Pollution Control Board | 2023-01-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹27,79,61,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,391.263 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 14 | |
| Units | 91 |
Unit types
| 3BHK (Unit -01) | 86.838 | 70 | TOWER 01 |
| 2BHK (Unit -02) | 44.809 | 9 | TOWER 01 |
| 2BHK (Unit -03 EWS) | 44.809 | 9 | TOWER 01 |
| Shop Floor | 14.3 | 3 | TOWER 01 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-04-01 | |
|---|---|---|
| Proposed completion | 2028-03-30 |
Quarterly progress
| 2024-Q1 | 2024-06-03 |
| 2023-Q4 | 2024-06-14 |
| 2024-Q2 | 2026-09-22 |
| 2024-Q3 | 2026-09-23 |
| 2024-Q4 | 2026-09-23 |
| 2025-Q1 | 2026-09-23 |
| 2025-Q2 | 2026-09-23 |
| 2025-Q3 | 2026-09-23 |
| 2025-Q4 | 2026-09-23 |
| 2026-Q1 | 2026-09-23 |
| 2026-Q2 | 2026-09-23 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AMARSONS AND ASSOCiATES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | NIRMAAN ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11675&inPromoter_ID=1733&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2022-04-22
- Building Permit Issue from Municipal Authority · 2023-01-05 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Defense Clearance · 2022-04-22
- Electric Substation NOC · 2023-06-16
- License as Promoter from competent Authority · 2022-05-11
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-04-18
- NOC from Mining Department · 2023-02-07
- Other Document (NOC for Forest Drainage National Highway) · 2023-08-03
- Other Document (NOC from MC regarding Sewage treatment) · 2022-06-29
- Pollution Clearance from Punjab Pollution Control Board · 2023-09-07
- Pollution Clearance from Punjab Pollution Control Board · 2023-01-30
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2022-04-22
- CLU Certificate
- Defense Clearance · 2022-04-22
- Electric Substation NOC · 2023-06-16
- License as Promoter from competent Authority · 2022-05-11
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-04-18
- NOC from Mining Department · 2023-02-07
- Other Document (NOC for Forest Drainage National Highway) · 2023-08-03
- Other Document (NOC from MC regarding Sewage treatment) · 2022-06-29
- Pollution Clearance from Punjab Pollution Control Board · 2023-09-07
- Pollution Clearance from Punjab Pollution Control Board · 2023-01-30
- 2024-Q1 · 2024-06-03
- 2023-Q4 · 2024-06-14
- 2024-Q2 · 2026-09-22
- 2024-Q3 · 2026-09-23
- 2024-Q4 · 2026-09-23
- 2025-Q1 · 2026-09-23
- 2025-Q2 · 2026-09-23
- 2025-Q3 · 2026-09-23
- 2025-Q4 · 2026-09-23
- 2026-Q1 · 2026-09-23
- 2026-Q2 · 2026-09-23
- 2026-Q3 · 2026-10-15