Overview
GANIYARI GREENS
AVNEESH TRIPATHI · BILASPUR
Units183
Booked45 of 183As of 2026-06-30
Construction progress90%As of 2026-06-30
Completion2027-02-14Revised · Proposed 2024-01-14
Registered on2019-01-25
Approvals3
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 30 quarters |
| Technical report | |
| Site & area | 3 site details · 183 unit types |
| Construction & progress | 4 progress details · 30 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 175 documents · 10 source links |
Registration
Registration
| Promoter | AVNEESH TRIPATHI | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA250119000902 | |
| Registered on | 2019-01-25 | |
| Project type | Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2024-01-14 | |
| Revised completion | 2027-02-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXA-2026-03458 | CG RERA | Complaint | Disposed | 2026-03-02 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,34,44,000 | |
|---|---|---|
| Construction | ₹1,28,83,000 |
Quarterly money flows
| 2019-Q1 | ₹1,39,000 |
| 2019-Q2 | ₹90,500 |
| 2019-Q3 | ₹3,10,366 |
| 2019-Q4 | ₹29,001 |
| 2020-Q1 | ₹3,63,740 |
| 2020-Q2 | ₹23,740 |
| 2020-Q3 | ₹3,49,340 |
| 2020-Q4 | ₹25,290 |
| 2021-Q1 | ₹1,36,790 |
| 2021-Q2 | ₹6,790 |
| 2021-Q3 | ₹8,280 |
| 2021-Q4 | ₹5,280 |
| 2022-Q1 | ₹5,280 |
| 2022-Q2 | ₹5,280 |
| 2022-Q3 | ₹1,174 |
| 2022-Q4 | ₹5,280 |
| 2023-Q1 | ₹5,280 |
| 2023-Q2 | ₹5,280 |
| 2023-Q3 | ₹5,280 |
| 2023-Q4 | ₹5,280 |
| 2024-Q1 | ₹2,93,280 |
| 2024-Q2 | ₹3,280 |
| 2024-Q3 | ₹3,280 |
| 2024-Q4 | ₹3,280 |
| 2025-Q1 | ₹3,280 |
| 2025-Q2 | ₹3,280 |
| 2025-Q3 | ₹3,280 |
| 2025-Q4 | ₹3,280 |
| 2026-Q1 | ₹3,280 |
| 2026-Q2 | ₹3,280 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 183 | |
|---|---|---|
| Booked | 45 | |
| Booked as of | 2026-06-30 |
Unit types
| Plot-Plot | 1 | 0 |
| BLOCK A-1 | 1 | 0 |
| BLOCK A-2 | 1 | 0 |
| BLOCK A-3 | 1 | 0 |
| BLOCK A-4 | 1 | 0 |
| BLOCK A-5 | 1 | 0 |
| BLOCK A-6 | 1 | 0 |
| BLOCK A-7 | 1 | 1 |
| BLOCK A-8 | 1 | 1 |
| BLOCK A-9 | 1 | 1 |
| BLOCK A-10 | 1 | 1 |
| BLOCK A-11 | 1 | 1 |
| BLOCK A-12 | 1 | 0 |
| BLOCK A-13 | 1 | 1 |
| BLOCK A-14 | 1 | 1 |
| BLOCK A-15 | 1 | 0 |
| BLOCK A-16 | 1 | 1 |
| BLOCK A-17 | 1 | 0 |
| BLOCK A-18 | 1 | 0 |
| BLOCK A-19 | 1 | 0 |
| BLOCK A-20 | 1 | 1 |
| BLOCK A-21 | 1 | 1 |
| BLOCK A-22 | 1 | 1 |
| BLOCK A-23 | 1 | 0 |
| BLOCK A-24 | 1 | 0 |
| BLOCK A-25 | 1 | 0 |
| BLOCK A-26 | 1 | 0 |
| BLOCK A-27 | 1 | 1 |
| BLOCK A-28 | 1 | 0 |
| BLOCK A-29 | 1 | 1 |
| BLOCK A-30 | 1 | 1 |
| BLOCK A-31 | 1 | 1 |
| BLOCK A-32 | 1 | 1 |
| BLOCK A-33 | 1 | 1 |
| BLOCK A-34 | 1 | 1 |
| BLOCK A-35 | 1 | 0 |
| BLOCK A-36 | 1 | 1 |
| BLOCK A-37 | 1 | 1 |
| BLOCK A-38 | 1 | 0 |
| BLOCK A-39 | 1 | 1 |
| BLOCK A-40 | 1 | 1 |
| BLOCK A-41 | 1 | 1 |
| BLOCK A-42 | 1 | 0 |
| BLOCK A-43 | 1 | 0 |
| BLOCK A-44 | 1 | 0 |
| BLOCK A-45 | 1 | 0 |
| BLOCK A-46 | 1 | 0 |
| BLOCK A-47 | 1 | 0 |
| BLOCK A-48 | 1 | 0 |
| BLOCK A-49 | 1 | 0 |
| BLOCK A-50 | 1 | 0 |
| BLOCK A-51 | 1 | 0 |
| BLOCK A-52 | 1 | 0 |
| BLOCK A-53 | 1 | 0 |
| BLOCK A-54 | 1 | 0 |
| BLOCK A-55 | 1 | 0 |
| BLOCK A-56 | 1 | 0 |
| BLOCK A-57 | 1 | 0 |
| BLOCK A-58 | 1 | 0 |
| BLOCK A-59 | 1 | 0 |
| BLOCK A-60 | 1 | 0 |
| BLOCK A-61 | 1 | 0 |
| BLOCK A-62 | 1 | 0 |
| BLOCK A-63 | 1 | 0 |
| BLOCK A-64 | 1 | 0 |
| BLOCK A-65 | 1 | 0 |
| BLOCK A-66 | 1 | 0 |
| BLOCK A-67 | 1 | 0 |
| BLOCK A-68 | 1 | 0 |
| BLOCK A-69 | 1 | 1 |
| BLOCK A-70 | 1 | 1 |
| BLOCK A-71 | 1 | 1 |
| BLOCK A-72 | 1 | 1 |
| BLOCK A-73 | 1 | 1 |
| BLOCK A-74 | 1 | 1 |
| BLOCK A-75 | 1 | 1 |
| BLOCK A-76 | 1 | 1 |
| BLOCK A-77 | 1 | 1 |
| BLOCK A-78 | 1 | 1 |
| BLOCK A-79 | 1 | 1 |
| BLOCK A-80 | 1 | 0 |
| BLOCK A-81 | 1 | 0 |
| BLOCK A-82 | 1 | 1 |
| BLOCK A-83 | 1 | 1 |
| BLOCK A-84 | 1 | 0 |
| BLOCK A-85 | 1 | 0 |
| BLOCK A-86 | 1 | 0 |
| BLOCK A-87 | 1 | 0 |
| BLOCK A-88 | 1 | 0 |
| BLOCK A-89 | 1 | 0 |
| BLOCK A-90 | 1 | 0 |
| BLOCK A-91 | 1 | 0 |
| BLOCK A-92 | 1 | 0 |
| BLOCK A-93 | 1 | 0 |
| BLOCK A-94 | 1 | 0 |
| BLOCK A-95 | 1 | 0 |
| BLOCK A-96 | 1 | 0 |
| BLOCK A-97 | 1 | 0 |
| BLOCK A-98 | 1 | 0 |
| BLOCK A-99 | 1 | 0 |
| BLOCK A-100 | 1 | 0 |
| BLOCK A-101 | 1 | 0 |
| BLOCK A-102 | 1 | 0 |
| BLOCK A-103 | 1 | 0 |
| BLOCK A-104 | 1 | 0 |
| BLOCK A-105 | 1 | 0 |
| BLOCK A-106 | 1 | 0 |
| BLOCK A-107 | 1 | 0 |
| BLOCK A-108 | 1 | 0 |
| BLOCK A-109 | 1 | 0 |
| BLOCK A-110 | 1 | 0 |
| BLOCK A-111 | 1 | 0 |
| BLOCK A-112 | 1 | 0 |
| BLOCK A-113 | 1 | 0 |
| BLOCK A-114 | 1 | 0 |
| BLOCK A-115 | 1 | 0 |
| BLOCK A-116 | 1 | 0 |
| BLOCK A-117 | 1 | 0 |
| BLOCK A-118 | 1 | 0 |
| BLOCK A-119 | 1 | 0 |
| BLOCK A-120 | 1 | 0 |
| BLOCK A-121 | 1 | 0 |
| BLOCK A-122 | 1 | 0 |
| BLOCK A-123 | 1 | 0 |
| BLOCK A-124 | 1 | 0 |
| BLOCK A-125 | 1 | 0 |
| BLOCK A-126 | 1 | 0 |
| BLOCK A-127 | 1 | 0 |
| BLOCK A-128 | 1 | 0 |
| BLOCK A-129 | 1 | 0 |
| BLOCK A-130 | 1 | 0 |
| BLOCK A-131 | 1 | 0 |
| BLOCK A-132 | 1 | 0 |
| BLOCK A-133 | 1 | 0 |
| BLOCK A-134 | 1 | 0 |
| BLOCK A-135 | 1 | 0 |
| BLOCK A-136 | 1 | 1 |
| BLOCK A-137 | 1 | 0 |
| BLOCK A-138 | 1 | 0 |
| BLOCK A-139 | 1 | 0 |
| BLOCK L-1 | 1 | 0 |
| BLOCK L-2 | 1 | 0 |
| BLOCK L-3 | 1 | 0 |
| BLOCK L-4 | 1 | 0 |
| BLOCK L-5 | 1 | 0 |
| BLOCK L-6 | 1 | 0 |
| BLOCK L-7 | 1 | 1 |
| BLOCK L-8 | 1 | 1 |
| BLOCK L-9 | 1 | 0 |
| BLOCK L-10 | 1 | 0 |
| BLOCK L-11 | 1 | 0 |
| BLOCK L-12 | 1 | 0 |
| BLOCK L-13 | 1 | 0 |
| BLOCK L-14 | 1 | 0 |
| BLOCK L-15 | 1 | 1 |
| BLOCK L-16 | 1 | 1 |
| BLOCK L-17 | 1 | 0 |
| BLOCK L-18 | 1 | 0 |
| BLOCK L-19 | 1 | 1 |
| BLOCK L-20 | 1 | 0 |
| BLOCK L-21 | 1 | 0 |
| BLOCK L-22 | 1 | 0 |
| BLOCK L-23 | 1 | 0 |
| BLOCK L-24 | 1 | 0 |
| BLOCK L-25 | 1 | 0 |
| BLOCK L-26 | 1 | 0 |
| BLOCK L-27 | 1 | 0 |
| BLOCK L-28 | 1 | 0 |
| BLOCK L-29 | 1 | 1 |
| BLOCK L-30 | 1 | 1 |
| BLOCK L-31 | 1 | 0 |
| BLOCK L-32 | 1 | 1 |
| BLOCK L-33 | 1 | 0 |
| BLOCK L-34 | 1 | 0 |
| BLOCK L-35 | 1 | 0 |
| BLOCK L-36 | 1 | 0 |
| BLOCK L-37 | 1 | 0 |
| BLOCK L-38 | 1 | 0 |
| BLOCK L-39 | 1 | 0 |
| BLOCK L-40 | 1 | 0 |
| BLOCK L-41 | 1 | 0 |
| BLOCK L-42 | 1 | 0 |
| BLOCK L-43 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 90% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2024-01-14 | |
| Revised completion | 2027-02-14 |
Quarterly progress
| 2019-Q1 | 21% |
| 2019-Q2 | 21% |
| 2019-Q3 | 41% |
| 2019-Q4 | 41% |
| 2020-Q1 | 41% |
| 2020-Q2 | 41% |
| 2020-Q3 | 41% |
| 2020-Q4 | 41% |
| 2021-Q1 | 41% |
| 2021-Q2 | 0% |
| 2021-Q3 | 52% |
| 2021-Q4 | 54% |
| 2022-Q1 | 56% |
| 2022-Q2 | 56% |
| 2022-Q3 | 59% |
| 2022-Q4 | 59% |
| 2023-Q1 | 59% |
| 2023-Q2 | 59% |
| 2023-Q3 | 59% |
| 2023-Q4 | 59% |
| 2024-Q1 | 69% |
| 2024-Q2 | 79% |
| 2024-Q3 | 90% |
| 2024-Q4 | 90% |
| 2025-Q1 | 90% |
| 2025-Q2 | 90% |
| 2025-Q3 | 90% |
| 2025-Q4 | 90% |
| 2026-Q1 | 90% |
| 2026-Q2 | 90% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AVNEESH TRIPATHI | |
|---|---|---|
| Type | Individual | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTAwNw==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-03-02 · Sign in to download
- Interim order · 2026-01-28 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- SM-EXA-2026-03458 · Sign in to download