Overview
GAURI SHANKAR VIHAR
PREETAK BAJPAYEE · RAJNANDGAON
Units96
Booked87 of 96As of 2022-03-31
Construction progress100%As of 2022-03-31
Completion2022-09-30Revised · Proposed 2021-12-30
Registered on2020-03-03
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 9 quarters |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 4 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 69 documents · 6 source links |
Registration
Registration
| Promoter | PREETAK BAJPAYEE | |
|---|---|---|
| District | RAJNANDGAON | |
| Regulator | CG RERA | |
| Registration number | PCGRERA030320001099 | |
| Registered on | 2020-03-03 | |
| Project type | Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2021-12-30 | |
| Revised completion | 2022-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,62,29,000 | |
|---|---|---|
| Construction | ₹2,60,81,000 |
Quarterly money flows
| 2020-Q1 | ₹15,82,087.4 |
| 2020-Q2 | ₹4,52,160.6 |
| 2020-Q3 | ₹8,24,281.8 |
| 2020-Q4 | ₹61,576.4 |
| 2021-Q1 | ₹9,50,681.42 |
| 2021-Q2 | ₹3,19,184.62 |
| 2021-Q3 | ₹1,89,167.02 |
| 2021-Q4 | ₹59,167.02 |
| 2022-Q1 | ₹5,633.02 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 96 | |
|---|---|---|
| Booked | 87 | |
| Booked as of | 2022-03-31 |
Unit types
| Type | Units | Booked |
|---|---|---|
| PREETAK BAJPAYEE (GAURU SHANKA | 96 | 87 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2022-03-31 | |
| Proposed completion | 2021-12-30 | |
| Revised completion | 2022-09-30 |
Quarterly progress
| 2020-Q1 | 46% |
| 2020-Q2 | 18% |
| 2020-Q3 | 22% |
| 2020-Q4 | 26% |
| 2021-Q1 | 60% |
| 2021-Q2 | 60% |
| 2021-Q3 | 85% |
| 2021-Q4 | 100% |
| 2022-Q1 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PREETAK BAJPAYEE | |
|---|---|---|
| Type | Other | |
| Escrow bank | Bandhan Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTM2OA==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Document
- Sanctioned Layout Plan
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities