Overview
GBN TAPESHWAR ENCLAVE
VAISHNAVI BUILDER AND DEVELOPER · Patna
Units37
Booked0 of 37As of 2026-06-30
Construction progress10%As of 2026-06-30
Completion2029-08-23Proposed
Registered on2026-03-30
Valid to2029-08-23
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 3 unit types |
| Construction & progress | 4 progress details · 2 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 9 source links |
Registration
Registration
| Promoter | VAISHNAVI BUILDER AND DEVELOPER | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP196828070326230829E00 | |
| Registered on | 2026-03-30 | |
| Valid to | 2029-08-23 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-08-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | NAGAR PARISHID DANAPUR NIZAMAT | |
| NOC From Airport Authority of India | ||
| NOC from Fire Service Authority | ||
| Notice of Commencement in form X | ||
| Environment Clearance | 2035-12-31 | |
| Fire NOC | 2029-08-23 | PROVISIONAL |
| Airport NOC | 2035-12-31 | |
| Water Supply Permission | 2035-12-31 | YES |
| Other approval | 2035-12-31 | NO |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,90,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,261 | |
|---|---|---|
| Built-up (m²) | 2,696.71 | |
| FAR | 2.13 | |
| Towers | 2 | |
| Units | 37 | |
| Booked | 0 | |
| Booked as of | 2026-06-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Shop | 9 | GBN TAPESHWAR ENCLAVE |
| 3 BHK | 16 | GBN TAPESHWAR ENCLAVE |
| 1 BHK | 12 | GBN TAPESHWAR ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 10% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2022-12-20 | |
| Proposed completion | 2029-08-23 |
Quarterly progress
| Quarter | Filed on | Progress | Booked |
|---|---|---|---|
| 2026-Q2 | 2026-07-30 | 10% | 0 |
| 2026-Q1 | 2026-05-28 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VAISHNAVI BUILDER AND DEVELOPER | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP11182022160132-2
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP11182022160132&ld=pan&pj=RERAP11182022160132-2&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP11182022160132-2
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Auditors Report/3 AC/3CB/3CD and Directors Report · Sign in to download
- Balance Sheet with Notes · Sign in to download
- Cash Flow Statement · Sign in to download
- Profit Loss Statement with Notes. · Sign in to download
- A brief detail of the project launched by the Promoter, in the past five years, a) whether already completed or being developed, b) including the current status of the said projects, c) any delay in its completion, d) details of cases pending, e) details of the type of land and f) payment pending. · Sign in to download
- A certificate from a Chartered accountant declaring that no advance booking amount has been taken from the customers against the current project duly signed by the promoter and countersigned by CA · Sign in to download
- Declaration (Form B) · Sign in to download
- Details of all the projects taken up by the Directors of the Company in other capacities, either individual or as part of other entities, during the last five years along with the details of cases filed in the projects as mentioned by the Promoter and orders passed in the cases · Sign in to download
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-30
- Q4 (Jan - Mar) / 2025-2026 · 2026-05-28
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- 2026-Q1 · 2026-05-28