Overview
GEEDES MOSAIC
ARUP BARMAN · SANDHYACHAL NAGAR
Units20
Booked0 of 20
Completion2024-12-31Revised · Proposed 2024-12-31
Registered on2024-11-18
Valid to2025-12-31
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 24 documents · 6 source links |
Registration
Registration
| Promoter | ARUP BARMAN | |
|---|---|---|
| District | KAMRUP METRO | |
| Locality | SANDHYACHAL NAGAR | |
| Regulator | RERA Assam | |
| Registration number | RERAA KM 112 OF 2024-2025 | |
| Registered on | 2024-11-18 | |
| Valid to | 2025-12-31 | |
| Status (as filed) | Registration Expired | |
| Proposed completion | 2024-12-31 | |
| Revised completion | 2024-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | |||
| Building Plan | |||
| NOC/Building Permit | GMC/W27/0295/25082021 | 2022-04-30 | 2025-04-30 |
| I. OFFICE OF THE GUWAHATI MUNICIPAL CORPORATION | 2022-04-30 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Registration Expired | |
|---|---|---|
| Valid to | 2025-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹4,40,32,000 | |
| Total | ₹4,54,75,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 936.65 | |
|---|---|---|
| Units | 20 | |
| Booked | 0 |
Unit types
| Type | Units | Booked |
|---|---|---|
| APARTMENT/SHOPS/OTHER BUILDINGS Type | 20 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-01-06 | |
|---|---|---|
| Proposed completion | 2024-12-31 | |
| Revised completion | 2024-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ARUP BARMAN | |
|---|---|---|
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/1011
- https://rera.assam.gov.in/view_project/searchprojectDetail/1011
- Registration Certificate
- Occupancy Certificate · Sign in to download
- Cumulative QPR
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2023-11-28 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2023-11-28 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2023-11-28 · Sign in to download
- POWER OF ATTORNEY · 2023-11-28 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2023-11-28 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2023-11-28 · Sign in to download
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2023-11-28 · Sign in to download
- PLANNING PERMIT FROM COMPETENT AUTHORITY · 2023-11-28
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2023-11-28 · Sign in to download
- CARPET AREA AND PARKING AREA DETAILS · 2023-11-28 · Sign in to download
- FIRE NOC · 2023-11-28
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2023-11-28 · Sign in to download
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2023-11-28 · Sign in to download
- PLAN OF DEVELOPMENT WORKS · 2023-11-28
- FORM B, DULY NOTARIZED · 2023-11-28 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2023-11-28
- Other · 2023-11-28 · Sign in to download
- Project application order/letter · 2024-10-01 · Sign in to download
- Project application order/letter · 2024-09-09 · Sign in to download
- Project application order/letter · 2024-08-17 · Sign in to download
- Project application order/letter · 2023-12-21 · Sign in to download
- Occupancy certificate · Sign in to download