Overview
GEETA NUTAN ENCLAVE
SADHAVI BUILDERS PRIVATE LIMITED · Patna
Units24
Completion2022-12-31Proposed
Registered on2020-08-12
Approvals1
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 2 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 16 documents · 12 source links |
Registration
Registration
| Promoter | SADHAVI BUILDERS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00186-2/1130/2020 | |
| Registered on | 2020-08-12 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status |
|---|---|---|---|
| RERA/CC/1166/2021 | RERA Bihar | Complaint | |
| RERA/C-CASE-370/2022 Execution Case No. 291/2024 | RERA Bihar | Pending |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹50,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 975.18 | |
|---|---|---|
| Built-up (m²) | 2,222.46 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 24 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 12 | GEETA NUTAN ENCLAVE |
| 3 BHK | 12 | GEETA NUTAN ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-01-14 | |
|---|---|---|
| Proposed completion | 2022-12-31 |
Quarterly progress
| 2021-Q2 | 2024-07-25 |
| 2021-Q1 | 2024-07-25 |
| 2020-Q4 | 2024-07-25 |
| 2020-Q3 | 2024-07-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SADHAVI BUILDERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Corporation Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP63201800186-2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP63201800186-2
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2021-2022 · 2024-07-25
- Q4-Jan to Mar / 2020-2021 · 2024-07-25
- Q3-Oct to Dec / 2020-2021 · 2024-07-25
- Q2-Jul to Sep / 2020-2021 · 2024-07-25
- Case proceeding RERA/CC/1166/2021 · 2022-07-04 · Sign in to download
- Case proceeding RERA/C-CASE-370/2022 Execution Case No. 291/2024 · 2025-07-07 · Sign in to download
- Case proceeding RERA/C-CASE-370/2022 Execution Case No. 291/2024 · 2025-12-29 · Sign in to download
- Other · 2022-07-04 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- RERA/CC/1166/2021 · Sign in to download
- RERA/C-CASE-370/2022 Execution Case No. 291/2024 · Sign in to download
- 2021-Q2 · 2024-07-25
- 2021-Q1 · 2024-07-25
- 2020-Q4 · 2024-07-25
- 2020-Q3 · 2024-07-25