Overview
GEETANJALI ERA
BILASPUR HOUSING PVT. LTD. · BILASPUR
Units113
Booked82 of 113As of 2026-06-30
Construction progress90%As of 2026-06-30
Completion2027-07-31Revised · Proposed 2026-12-31
Registered on2021-03-12
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 2 cost heads · 22 quarters |
| Technical report | |
| Site & area | 3 site details · 113 unit types |
| Construction & progress | 4 progress details · 22 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 127 documents · 5 source links |
Registration
Registration
| Promoter | BILASPUR HOUSING PVT. LTD. | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA120321001210 | |
| Registered on | 2021-03-12 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2026-12-31 | |
| Revised completion | 2027-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,46,93,000 | |
|---|---|---|
| Construction | ₹9,34,89,000 |
Quarterly money flows
| 2021-Q1 | ₹1,40,000 |
| 2021-Q2 | ₹19,800 |
| 2021-Q3 | ₹1,66,37,531 |
| 2021-Q4 | ₹4,45,081.4 |
| 2022-Q1 | ₹18,00,407.1 |
| 2022-Q2 | ₹277.1 |
| 2022-Q3 | ₹4,90,277 |
| 2022-Q4 | ₹51,75,768.52 |
| 2023-Q1 | ₹8,47,785.04 |
| 2023-Q2 | ₹735.04 |
| 2023-Q3 | ₹35.03 |
| 2023-Q4 | ₹22,12,280.02 |
| 2024-Q1 | ₹0 |
| 2024-Q2 | ₹0 |
| 2024-Q3 | ₹0 |
| 2024-Q4 | ₹0.7 |
| 2025-Q1 | ₹9,34,500.7 |
| 2025-Q2 | ₹9,34,500.7 |
| 2025-Q3 | ₹44,98,725.7 |
| 2025-Q4 | ₹15,51,200 |
| 2026-Q1 | ₹53,19,528.48 |
| 2026-Q2 | ₹43,928 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 113 | |
|---|---|---|
| Booked | 82 | |
| Booked as of | 2026-06-30 |
Unit types
| A-1 | 1 | 1 |
| A-2 | 1 | 1 |
| A-3 | 1 | 1 |
| A-4 | 1 | 1 |
| A-5 | 1 | 1 |
| A-6 | 1 | 1 |
| A-7 | 1 | 1 |
| A-8 | 1 | 0 |
| A-9 | 1 | 1 |
| A-10 | 1 | 1 |
| A-11 | 1 | 1 |
| A-12 | 1 | 1 |
| A-13 | 1 | 1 |
| A-14 | 1 | 1 |
| A-15 | 1 | 1 |
| A-16 | 1 | 0 |
| A-17 | 1 | 0 |
| A-18 | 1 | 1 |
| A-19 | 1 | 1 |
| A-20 | 1 | 1 |
| A-21 | 1 | 1 |
| A-22 | 1 | 1 |
| A-23 | 1 | 1 |
| A-24 | 1 | 1 |
| A-25 | 1 | 1 |
| A-26 | 1 | 1 |
| A-27 | 1 | 1 |
| A-28 | 1 | 1 |
| A-29 | 1 | 1 |
| A-30 | 1 | 1 |
| A-31 | 1 | 1 |
| A-32 | 1 | 1 |
| A-33 | 1 | 1 |
| A-34 | 1 | 1 |
| A-35 | 1 | 1 |
| A-36 | 1 | 1 |
| A-37 | 1 | 1 |
| A-38 | 1 | 1 |
| A-39 | 1 | 1 |
| A-40 | 1 | 0 |
| A-41 | 1 | 1 |
| A-42 | 1 | 1 |
| A-43 | 1 | 0 |
| A-44 | 1 | 0 |
| A-45 | 1 | 0 |
| A-46 | 1 | 0 |
| A-47 | 1 | 0 |
| A-48 | 1 | 0 |
| A-49 | 1 | 0 |
| A-50 | 1 | 0 |
| A-51 | 1 | 1 |
| A-52 | 1 | 1 |
| A-53 | 1 | 1 |
| A-54 | 1 | 1 |
| A-55 | 1 | 1 |
| A-56 | 1 | 1 |
| A-57 | 1 | 1 |
| A-58 | 1 | 1 |
| A-59 | 1 | 1 |
| A-60 | 1 | 1 |
| A-61 | 1 | 0 |
| A-62 | 1 | 0 |
| A-63 | 1 | 0 |
| A-64 | 1 | 1 |
| A-65 | 1 | 1 |
| A-66 | 1 | 1 |
| A-67 | 1 | 1 |
| A-68 | 1 | 0 |
| A-69 | 1 | 0 |
| A-70 | 1 | 1 |
| A-71 | 1 | 0 |
| A-72 | 1 | 0 |
| A-73 | 1 | 0 |
| A-74 | 1 | 0 |
| A-75 | 1 | 0 |
| A-76 | 1 | 1 |
| A-77 | 1 | 0 |
| A-78 | 1 | 0 |
| A-79 | 1 | 1 |
| A-80 | 1 | 1 |
| A-81 | 1 | 1 |
| B-1 | 1 | 1 |
| B-2 | 1 | 1 |
| B-3 | 1 | 1 |
| B-4 | 1 | 1 |
| B-5 | 1 | 1 |
| B-6 | 1 | 1 |
| B-7 | 1 | 1 |
| B-8 | 1 | 1 |
| B-9 | 1 | 1 |
| B-10 | 1 | 1 |
| B-11 | 1 | 1 |
| B-12 | 1 | 1 |
| B-13 | 1 | 1 |
| B-14 | 1 | 1 |
| B-15 | 1 | 1 |
| B-16 | 1 | 1 |
| B-17 | 1 | 1 |
| B-18 | 1 | 1 |
| B-19 | 1 | 1 |
| B-20 | 1 | 1 |
| B-21 | 1 | 1 |
| B-22 | 1 | 1 |
| B-23 | 1 | 1 |
| B-24 | 1 | 1 |
| B-25 | 1 | 0 |
| B-26 | 1 | 0 |
| B-27 | 1 | 0 |
| B-28 | 1 | 0 |
| B-29 | 1 | 0 |
| B-30 | 1 | 0 |
| B-31 | 1 | 0 |
| C-1 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 90% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2026-12-31 | |
| Revised completion | 2027-07-31 |
Quarterly progress
| 2021-Q1 | 0% |
| 2021-Q2 | 0% |
| 2021-Q3 | 0% |
| 2021-Q4 | 0% |
| 2022-Q1 | 0% |
| 2022-Q2 | 20% |
| 2022-Q3 | 20% |
| 2022-Q4 | 20% |
| 2023-Q1 | 25% |
| 2023-Q2 | 25% |
| 2023-Q3 | 33% |
| 2023-Q4 | 55% |
| 2024-Q1 | 58% |
| 2024-Q2 | 58% |
| 2024-Q3 | 58% |
| 2024-Q4 | 58% |
| 2025-Q1 | 60% |
| 2025-Q2 | 90% |
| 2025-Q3 | 90% |
| 2025-Q4 | 90% |
| 2026-Q1 | 90% |
| 2026-Q2 | 90% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BILASPUR HOUSING PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTUwNQ==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities