Overview
GG TOWN WAGHOLI PHASE B BUILDING 8 AND 9
Overview
GG TOWN WAGHOLI PHASE B BUILDING 8 AND 9
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | 1 | – | – | Red flag |
| Disputes & cases | 1 | – | – | Red flag |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | ||||
Title & ownership
We haven't verified this for this project yet.
Sign in first, then it is one click.
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Jun 2028 | |
| Registration status | Deregistered | Red flag |
| Registration number | P52100026847 | |
|---|---|---|
Disputes & cases
Builder: GOEL GANGA INDIA PVT LTD
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| Other status 1 | ||||||
| – | 135 | CIVIL COURT PUNE | WAGHOLI NEAR RMC GARDEN | – | Filed case | –, Medium: The record does not say whether it is decided. |
17 other registrations under this promoter's exact name in Maharashtra; a complaint on one is listed when MahaRERA lists it.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
No documents are filed for this phase.
Source: MahaRERA project page and the documents filed there, as read by us. 55 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| – |
| – |
| – |
| – |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
All projects in Pune → (12 of 4,377 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| Registered |
|---|
| 31 Oct 2020 |
| Projects within 4 km, counted |
|---|
| 23 (23 with an approximate location) |
| Flats in them | 2,802 |
|---|
| Sold or booked | 2,029 of 2,802 (72%) |
|---|
| Unsold | 773 |
|---|
Well within 3 km of filed pin; not a site reading.
| Groundwater | monitoring well, 2026-01-10: 4.1 m below ground |
|---|
| RERA completion date | 30 Jun 2028 | |
|---|---|---|
| Registered | 31 Oct 2020 |
Land · ₹1.54 Cr 1.7%Development · ₹91.61 Cr 98.3%
| Estimated cost, at registration | ₹93.15 Cr |
|---|
| Registration at MahaRERA | Deregistered |
|---|
| Other phases under this promoter name | 14 | |
|---|---|---|
| With a filed extension or completion | 4 (0 completed, 4 extended) | |
| Average schedule slip | 8 months |