Overview
GILLCO VALLEY
GILLCO DEVELOPERS AND BUILDERS PVT LTD · Sahibzada Ajit Singh Nagar (Mohali)
Completion2020-12-31Proposed
Valid to2020-12-31
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 1 site detail |
| Construction & progress | 2 progress details · 35 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 18 documents · 44 source links |
Registration
Registration
| Promoter | GILLCO DEVELOPERS AND BUILDERS PVT LTD | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS80-PR0038 | |
| Valid to | 2020-12-31 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2020-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| CLU Certificate | |
| Electric Substation NOC | 2011-12-09 |
| Environment Clearance certificate/ NOC | 2015-10-01 |
| License as Promoter from competent Authority | 2010-10-10 |
| License to develop colony or society from Competent Authority |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹88,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,34,789 |
|---|
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-05-31 | |
|---|---|---|
| Proposed completion | 2020-12-31 |
Quarterly progress
| 2018-Q3 | 2022-06-06 |
| 2018-Q4 | 2022-06-06 |
| 2019-Q1 | 2022-06-06 |
| 2019-Q2 | 2022-06-06 |
| 2019-Q3 | 2022-06-06 |
| 2019-Q4 | 2022-06-06 |
| 2020-Q1 | 2022-06-06 |
| 2020-Q2 | 2022-06-06 |
| 2020-Q3 | 2022-06-06 |
| 2021-Q1 | 2022-06-06 |
| 2021-Q2 | 2022-06-06 |
| 2021-Q3 | 2022-06-06 |
| 2021-Q4 | 2022-06-06 |
| 2022-Q1 | 2022-06-06 |
| 2020-Q4 | 2022-06-16 |
| 2022-Q2 | 2023-12-06 |
| 2022-Q3 | 2023-12-06 |
| 2022-Q4 | 2023-12-06 |
| 2023-Q1 | 2023-12-06 |
| 2023-Q2 | 2023-12-06 |
| 2023-Q3 | 2023-12-06 |
| 2023-Q4 | 2024-01-24 |
| 2024-Q1 | 2024-04-25 |
| 2024-Q2 | 2024-08-02 |
| 2024-Q3 | 2024-12-16 |
| 2024-Q4 | 2025-01-07 |
| 2025-Q1 | 2025-04-18 |
| 2018-Q1 | 2025-07-13 |
| 2018-Q2 | 2025-07-13 |
| 2025-Q2 | 2025-07-13 |
| 2025-Q3 | 2025-10-25 |
| 2025-Q4 | 2026-01-10 |
| 2026-Q1 | 2026-04-10 |
| 2026-Q2 | 2026-07-13 |
| 2026-Q3 | 2026-10-14 |
Extensions
| Valid to |
|---|
| 2022-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GILLCO DEVELOPERS AND BUILDERS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 5 |
Professional firms
| Role | Firm |
|---|---|
| Architect | DHAM CONSULTANTS |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10633&inPromoter_ID=1522&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2011-12-09
- Environment Clearance certificate/ NOC · 2015-10-01
- License as Promoter from competent Authority · 2010-10-10
- License to develop colony or society from Competent Authority
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2011-12-09
- Environment Clearance certificate/ NOC · 2015-10-01
- License as Promoter from competent Authority · 2010-10-10
- License to develop colony or society from Competent Authority
- Extension order · Sign in to download
- 2018-Q3 · 2022-06-06
- 2018-Q4 · 2022-06-06
- 2019-Q1 · 2022-06-06
- 2019-Q2 · 2022-06-06
- 2019-Q3 · 2022-06-06
- 2019-Q4 · 2022-06-06
- 2020-Q1 · 2022-06-06
- 2020-Q2 · 2022-06-06
- 2020-Q3 · 2022-06-06
- 2021-Q1 · 2022-06-06
- 2021-Q2 · 2022-06-06
- 2021-Q3 · 2022-06-06
- 2021-Q4 · 2022-06-06
- 2022-Q1 · 2022-06-06
- 2020-Q4 · 2022-06-16
- 2022-Q2 · 2023-12-06
- 2022-Q3 · 2023-12-06
- 2022-Q4 · 2023-12-06
- 2023-Q1 · 2023-12-06
- 2023-Q2 · 2023-12-06
- 2023-Q3 · 2023-12-06
- 2023-Q4 · 2024-01-24
- 2024-Q1 · 2024-04-25
- 2024-Q2 · 2024-08-02
- 2024-Q3 · 2024-12-16
- 2024-Q4 · 2025-01-07
- 2025-Q1 · 2025-04-18
- 2018-Q1 · 2025-07-13
- 2018-Q2 · 2025-07-13
- 2025-Q2 · 2025-07-13
- 2025-Q3 · 2025-10-25
- 2025-Q4 · 2026-01-10
- 2026-Q1 · 2026-04-10
- 2026-Q2 · 2026-07-13
- 2026-Q3 · 2026-10-14