GIRIJAPURI LAYOUT

CHINMAY DEVELOPERS · Belagavi
Completion2024-04-12Revised · Proposed 2023-07-12
Registered on2020-01-09
Valid to2024-04-12
Approvals2
Cases5
Complaints5

Sections

Property title & search report
Approvals2 approvals
Disputes & cases5 cases · 5 project complaints · 6 promoter complaints
Contract & costs3 cost heads
Technical report
Site & area1 site detail
Construction & progress3 progress details · 2 extensions
Developer & finance
Developer4 developer details
The evidence
Sources57 documents · 14 source links

Registration

Registration

PromoterCHINMAY DEVELOPERS
DistrictBelagavi
RegulatorK-RERA
Registration numberPRM/KA/RERA/1249/367/PR/200109/003140
Registered on2020-01-09
Valid to2024-04-12
Project typePlotted Development
Status (as filed)APPROVED
Proposed completion2023-07-12
Revised completion2024-04-12