Overview
Glenwood
Mesco Realtors LLP · Nadakkavu
Units43
Booked39 of 43
Construction progress98%
Completion2027-11-30Proposed
Registered on2022-09-02
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 10 unit types |
| Construction & progress | 3 progress details · 17 quarters |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 37 documents · 5 source links |
Registration
Registration
| Promoter | Mesco Realtors LLP | |
|---|---|---|
| District | Kozhikode | |
| Locality | Nadakkavu | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KKD/147/2022 | |
| Registered on | 2022-09-02 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2027-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | TP9/84941/2021 | 2022-06-20 | 2027-06-19 | Kozhikode Municipal Corporation |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,777 | |
|---|---|---|
| Built-up (m²) | 5,921.56 | |
| Towers | 0 | |
| Units | 43 | |
| Booked | 39 |
Unit types
| 1BHK | 1 | 0 | Glenwood |
| 1BHK | 1 | 0 | Glenwood |
| 1BHK | 1 | 1 | Glenwood |
| 1BHK | 1 | 1 | Glenwood |
| 2BHK | 2 | 2 | Glenwood |
| 2BHK | 12 | 11 | Glenwood |
| 3BHK | 11 | 11 | Glenwood |
| 3BHK | 2 | 1 | Glenwood |
| 3BHK | 11 | 11 | Glenwood |
| 3BHK | 1 | 1 | Glenwood |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 98% | |
|---|---|---|
| Start | 2022-06-20 | |
| Proposed completion | 2027-11-30 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q4 |
| 2023-2024 Q1 |
| 2023-2024 Q2 |
| 2023-2024 Q3 |
| 2022-2023 Q2 |
| 2022-2023 Q3 |
| 2022-2023 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Mesco Realtors LLP | |
|---|---|---|
| Type | LLP | |
| Escrow bank | Axis Bank | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Tropics Architects |
| Engineer | Mesco Realtors LLP |
| CA | Eshita Tarun and Associates |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11055
- https://rera.kerala.gov.in/projects?district=591&page=3
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=fNlAUORwBE7GPim4T6r2W8Wggqb%2B1zYkMAhzuZcMi1118bW8HTWyibCAjZqla7dII2AEw9AHV88F734Q1QzC4xQ3ZVPN0pk3Iz4JAIv6elzVaFkXHnPGerhqtr9lI8hCdDG9i8tEljKuUPjjibzONyOJC6bahrJ5U0U67uTcCymZ1UsRav5hZg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11055&Division=1&UserID=31856&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2022-09-02
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-03
- Copy of Valid Building Permit · 2022-08-03
- Detailed technical specifications to be adopted in the project · 2022-08-03 · Sign in to download
- Layout approval plan · 2022-08-23
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2022-08-03 · Sign in to download
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03
- Site Plan / Site Map · 2022-08-03