Overview
GLS LANSDOWNE
GLS INFRATECH PVT. LTD. · Gurugram
Units106
Completion2028-02-02Proposed
Registered on2023-05-08
Valid to2028-02-02
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 10 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 35 documents · 2 source links |
Registration
Registration
| Promoter | GLS INFRATECH PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/713/445/2023/57 DATED 08.05.2023 | |
| Registered on | 2023-05-08 | |
| Valid to | 2028-02-02 | |
| Status (as filed) | Registered | |
| Proposed completion | 2028-02-02 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 22 of 2023 dated 03.02.2023 | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. LICENSE | 2023-02-03 | ||
| II. CHANGE OF DEVELOPER | 2023-02-24 | ||
| III. FOREST NOC | 2022-11-21 | ||
| IV. ARAWALI NOC | 2022-12-15 | ||
| V. LAYOUT | 2023-02-03 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹50,40,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹1,06,96,65,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 106 |
|---|
Unit types
| Plot | 7 | |
| Plot | 4 | |
| Plot | 40 | |
| Plot | 17 | |
| Plot | 1 | |
| Plot | 10 | |
| Plot | 8 | |
| Plot | 8 | |
| Plot | 11 | |
| Apartment/Shops/Other Buildings | 1,133.053 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-04-03 | |
|---|---|---|
| Proposed completion | 2028-02-02 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GLS INFRATECH PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2377
- Registration Certificate · 2023-05-08
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2023-03-02
- CA CERTIFICATE · 2023-03-03 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2023-02-26
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2023-03-03 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2023-03-03 · Sign in to download
- COLLABORATION AGREEMENT · 2023-03-03 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2023-03-03 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2023-02-26
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2023-02-26
- DRAFT APPLICATION · 2023-03-03 · Sign in to download
- LOI · 2023-03-02 · Sign in to download
- LC - IV AND BILATERAL AGREEMENT · 2023-03-03 · Sign in to download
- SERVICE ESTIMATES · 2023-03-02 · Sign in to download
- CHANGE OF DEVELOPER · 2023-03-02 · Sign in to download
- FOREST NOC · 2023-02-26
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2023-03-02
- DRAFT BBA · 2023-03-03 · Sign in to download
- BANK UNDERTAKING · 2023-03-03 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2023-03-03 · Sign in to download
- DRAFT PAYMENT RECEIPT · 2023-03-03 · Sign in to download
- AKS · 2023-03-03 · Sign in to download
- JAMABANDI · 2023-03-03 · Sign in to download
- DRAFT ALLOTMENT LETTER · 2023-03-03 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2023-03-03 · Sign in to download
- ARAWALI NOC · 2023-02-26
- ZONING PLAN · 2023-03-02
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2023-03-02 · Sign in to download
- STORM WATER LAYOUT · 2023-03-02 · Sign in to download
- DEMAND DRAFT · 2023-03-03 · Sign in to download
- GPA · 2023-03-03 · Sign in to download
- DEMARCATION PLAN · 2023-03-02
- SEWERAGE LAYOUT · 2023-03-02 · Sign in to download
- ROAD LAYOUT · 2023-03-02 · Sign in to download
- MUTATION · 2023-03-03 · Sign in to download