Overview
GODREJ ARIA @ 101 ( VOL. I)
WONDER CITY BUILDCON PRIVATE LIMITED · Gurugram
Units1,993
Completion2021-02-28Revised
Registered on2017-08-17
Valid to2021-02-28
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 18 unit types |
| Construction & progress | 1 progress detail |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 2 source links |
Registration
Registration
| Promoter | WONDER CITY BUILDCON PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 61 OF 2017 DATED 17.8.2017 | |
| Registered on | 2017-08-17 | |
| Valid to | 2021-02-28 | |
| Status (as filed) | Registered | |
| Revised completion | 2021-02-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 47 of 2013 and 109 of 2014 | Town & Country Planning Department | |
| Layout Plan | 2015-08-07 | ||
| Building Plan | 2015-08-07 | ||
| I. LICENCE | 2013-06-06 | ||
| II. RENEWAL OF LICENCE | 2019-06-12 | ||
| III. ADDITIONAL LICENCE | 2014-08-14 | ||
| IV. RENEWAL OF ADDITIONAL LICENCE | 2019-09-30 | ||
| V. BUILDING PLAN | 2014-08-20 | ||
| VI. ADDITIONAL/REVISED BUILDING PLAN | 2015-08-07 | ||
| VII. ENVIRONMENT CLEARANCE | 2017-05-01 | ||
| VIII. FIRE SCHEME APPROVAL | 2017-12-12 | ||
| IX. SERVICE PLAN ESTIMATE | 2018-03-08 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹40,22,72,000 | |
|---|---|---|
| Construction | ₹2,63,25,80,000 | |
| Total | ₹4,12,73,83,999.9999995 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 55,062.439 | |
|---|---|---|
| FAR | 1,23,447.894 | |
| Units | 1,993 |
Unit types
| 1 | 74 |
| 2 | 102 |
| 3 | 99 |
| 4 | 107 |
| 5 | 100 |
| 6 | 105 |
| 7 | 98 |
| 8 | 104 |
| 9 | 92 |
| 10 | 84 |
| 11 | 89 |
| 12 | 99 |
| 13 | 100 |
| 14 | 149 |
| 15 | 158 |
| 16 | 151 |
| 17 | 131 |
| 18 | 151 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Revised completion | 2021-02-28 |
|---|
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | WONDER CITY BUILDCON PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1006
- Registration Certificate · 2017-08-17
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2019-11-28 · Sign in to download
- WONDER CITY BUILDCON PRIVATE LIMITED BALANCE SHEET 2019 · 2019-11-28 · Sign in to download
- DEVELOPMENT AGREEMENT · 2019-11-28 · Sign in to download
- DEMARCATION PLAN · 2019-11-28
- AGREEMENT FOR SALE · 2019-11-28 · Sign in to download
- WONDER CITY BUILDCON PRIVATE LIMITED BALANCE SHEET 2018 · 2019-11-28 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-11-28
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-11-28
- WONDER CITY BUILDCON PRIVATE LIMITED BALANCE SHEET 2017 · 2019-11-28 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-11-28 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-11-28 · Sign in to download
- ALLOTMENT LETTER · 2019-11-28 · Sign in to download
- ZONING PLAN · 2019-11-28
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-11-28
- GENERAL POWER OF ATTORNEY · 2019-11-28 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-11-28
- STATEMENT OF LIABILITIES AGAINST THE PROJECT · 2019-11-28 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-11-28
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-11-30 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-11-30 · Sign in to download
- Occupation Certificate · 2024-08-02 · Sign in to download
- Occupation Certificate · 2024-08-13 · Sign in to download