DOSLChhattisgarh Workspace

Overview

GOKUL DHAM PROJECT

SATGURU INFRAPROJECTS · KANKER
Units210
Booked115 of 210As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2025-12-15Revised · Proposed 2023-06-30
Registered on2018-07-10
Approvals2
Cases2

Sections

Property title & search report
Approvals2 approvals
Disputes & cases2 cases
Contract & costs2 cost heads · 30 quarters
Technical report
Site & area3 site details · 210 unit types
Construction & progress4 progress details · 30 quarters
Developer & finance
Developer3 developer details
The evidence
Sources192 documents · 9 source links

Registration

Registration

PromoterSATGURU INFRAPROJECTS
DistrictKANKER
RegulatorCG RERA
Registration numberPCGRERA100718000514
Registered on2018-07-10
Project typePlotted Development
Status (as filed)New
Proposed completion2023-06-30
Revised completion2025-12-15