Overview
GOLD LEAF
SANWARE INFRATECH · BILASPUR
Units90
Booked13 of 90As of 2026-06-30
Construction progress8%As of 2026-06-30
Completion2030-09-11Revised · Proposed 2030-05-11
Registered on2025-05-26
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 2 cost heads · 5 quarters |
| Technical report | |
| Site & area | 3 site details · 90 unit types |
| Construction & progress | 4 progress details · 5 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 40 documents · 7 source links |
Registration
Registration
| Promoter | SANWARE INFRATECH | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA260525001932 | |
| Registered on | 2025-05-26 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2030-05-11 | |
| Revised completion | 2030-09-11 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,61,97,000 | |
|---|---|---|
| Construction | ₹16,32,70,000 |
Quarterly money flows
| 2025-Q2 | ₹0 |
| 2025-Q3 | ₹0 |
| 2025-Q4 | ₹0 |
| 2026-Q1 | ₹35,000 |
| 2026-Q2 | ₹4,22,800 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 90 | |
|---|---|---|
| Booked | 13 | |
| Booked as of | 2026-06-30 |
Unit types
| 2BHK | 78.41 | 1 | 1 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 83.61 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 83.61 | 1 | 1 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 1 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 1 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 1 |
| 2BHK | 83.61 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 1 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 83.61 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 1 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 83.61 | 1 | 1 |
| 3BHK | 102.94 | 1 | 1 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 83.61 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 3BHK | 102.94 | 1 | 0 |
| 2BHK | 78.41 | 1 | 0 |
| 1BHK | 45.06 | 1 | 0 |
| 1BHK | 35.02 | 1 | 0 |
| 1BHK | 44.59 | 1 | 0 |
| 1BHK | 25.36 | 1 | 0 |
| 1BHK | 26.57 | 1 | 1 |
| 1BHK | 26.57 | 1 | 0 |
| 1BHK | 25.36 | 1 | 1 |
| 1BHK | 45.34 | 1 | 0 |
| 1BHK | 35.02 | 1 | 0 |
| 1BHK | 50.26 | 1 | 0 |
| 1BHK | 45.34 | 1 | 1 |
| 1BHK | 25.36 | 1 | 0 |
| 1BHK | 26.57 | 1 | 0 |
| 1BHK | 45.43 | 1 | 0 |
| 1BHK | 36.14 | 1 | 0 |
| 1BHK | 45.43 | 1 | 0 |
| 1BHK | 36.14 | 1 | 0 |
| 1BHK | 26.57 | 1 | 0 |
| 1BHK | 25.36 | 1 | 0 |
| 1BHK | 45.34 | 1 | 0 |
| 1BHK | 49.8 | 1 | 0 |
| 1BHK | 31.49 | 1 | 0 |
| 1BHK | 33.07 | 1 | 0 |
| 1BHK | 36.14 | 1 | 1 |
| 1BHK | 45.43 | 1 | 0 |
| 1BHK | 45.06 | 1 | 0 |
| 1BHK | 50.26 | 1 | 0 |
| 1BHK | 45.34 | 1 | 0 |
| 1BHK | 38.37 | 1 | 0 |
| 1BHK | 45.43 | 1 | 0 |
| 1BHK | 45.43 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 8% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2030-05-11 | |
| Revised completion | 2030-09-11 |
Quarterly progress
| 2025-Q2 | 2% |
| 2025-Q3 | 6% |
| 2025-Q4 | 7% |
| 2026-Q1 | 7% |
| 2026-Q2 | 8% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SANWARE INFRATECH | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjM3OQ==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities