Overview
GOLD TOWN SQUARE
Gold Town Infra LLP · Sahibzada Ajit Singh Nagar (Mohali)
Units21
Completion2029-01-15Proposed
Valid to2029-01-15
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 29 documents · 22 source links |
Registration
Registration
| Promoter | Gold Town Infra LLP | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PC0277 | |
| Valid to | 2029-01-15 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-01-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2025-08-26 |
| CLU Certificate | ||
| CLU Certificate | ||
| Electric Substation NOC | 2024-08-21 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2025-08-26 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2024-02-28 | |
| NOC from Mining Department | 2023-12-11 | |
| Other Document (Forest NOC) | 2023-12-12 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-09-09 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹14,51,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,180.602 | |
|---|---|---|
| Units | 21 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| PLOTs | 1,003.353 | 12 | COMMERCIAL PLOTS NO 01 TO 06 9 TO 14 |
| PLOTs | 189.522 | 2 | COMMERCIAL PLOTS NO 07 TO 08 |
| PLOTs | 327.762 | 7 | COMMERCIAL PLOT NO 15 TO 21 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-01-16 | |
|---|---|---|
| Proposed completion | 2029-01-15 |
Quarterly progress
| 2024-Q3 | 2025-02-03 |
| 2024-Q4 | 2025-02-03 |
| 2025-Q1 | 2025-05-21 |
| 2025-Q2 | 2025-11-21 |
| 2025-Q3 | 2025-11-21 |
| 2025-Q4 | 2026-08-07 |
| 2026-Q1 | 2026-08-07 |
| 2026-Q2 | 2026-08-07 |
| 2026-Q3 | 2026-10-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Gold Town Infra LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Others | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11873&inPromoter_ID=2764&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-08-26
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-08-21
- Environment Clearance certificate/ NOC · 2025-08-26
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-02-28
- NOC from Mining Department · 2023-12-11
- Occupancy Certificate from Municipal/ Competent Authority · 2024-06-24 · Sign in to download
- Other Document (DIARY NUMBER AAI EC ERASE REQUEST TO ADC UD ) · 2025-11-21 · Sign in to download
- Other Document (Forest NOC) · 2023-12-12
- Other Document (ROAD ACCESS CERTIFICATE) · 2025-08-25 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2025-09-09
- Consent details of actual owner of Land · Sign in to download
- Consent details of actual owner of Land · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-08-26
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2024-08-21
- Environment Clearance certificate/ NOC · 2025-08-26
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-02-28
- NOC from Mining Department · 2023-12-11
- Other Document (Forest NOC) · 2023-12-12
- Pollution Clearance from Punjab Pollution Control Board · 2025-09-09
- 2024-Q3 · 2025-02-03
- 2024-Q4 · 2025-02-03
- 2025-Q1 · 2025-05-21
- 2025-Q2 · 2025-11-21
- 2025-Q3 · 2025-11-21
- 2025-Q4 · 2026-08-07
- 2026-Q1 · 2026-08-07
- 2026-Q2 · 2026-08-07
- 2026-Q3 · 2026-10-11