Overview
Golden Woods
Shaurya Land Developers · Sahibzada Ajit Singh Nagar (Mohali)
Units247
Booked0 of 247As of 2026-09-30
Completion2032-06-25Proposed
Registered on2026-09-09
Valid to2032-06-25
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details · 30 unit types |
| Construction & progress | 2 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 15 source links |
Registration
Registration
| Promoter | Shaurya Land Developers | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR1438 | |
| Registered on | 2026-09-09 | |
| Valid to | 2032-06-25 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2032-06-25 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2025-04-22 | |
| CLU Certificate | ||
| CLU Certificate | ||
| Electric Substation NOC | 2026-06-25 | |
| Environment Clearance certificate/ NOC | 2025-10-24 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Mining Department | 2026-07-13 | |
| Other Document (Affidavit for NOC ) | Legal Documents (Received) | 2026-07-10 |
| Other Document (Clarification w.r.t. HT NOC) | Legal Documents (Received) | 2026-08-04 |
| Other Document (Forest NOC) | 2026-05-04 | |
| Pollution Clearance from Punjab Pollution Control Board | 2026-07-14 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,41,04,18,617 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 10,335.49 | |
|---|---|---|
| Towers | 6 | |
| Maximum floors | 17 | |
| Units | 247 | |
| Booked | 0 | |
| Booked as of | 2026-09-30 |
Unit types
| Flat No 101 to 104, 201 to 204, 301 to 304, 401 to 404, 501 to 504, 601 to 604, 701 to 704 | 89.51 | 28 | 0 | TOWER 1 - STILT PLUS 16 FLOORS - 3BHK |
| Flat No 801 to 804, 901 to 904, 1001 to 1004, 1101 to 1104, 1201 to 1204, 1301 to 1304, 1401 to 1404 | 89.51 | 28 | 0 | TOWER 1 - STILT PLUS 16 FLOORS - 3BHK |
| Flat No 1501 to 1504, 1601 to 1604 | 89.51 | 8 | 0 | TOWER 1 - STILT PLUS 16 FLOORS - 3BHK |
| Flat No 101 to 104, 201 to 204, 301 to 304, 401 to 404, 501 to 504, 601 to 604, 701 to 704 | 89.51 | 28 | 0 | TOWER 2 - STILT PLUS 16 FLOORS - 3BHK |
| Flat No 801 to 804, 901 to 904, 1001 to 1004, 1101 to 1104, 1201 to 1204, 1301 to 1304, 1401 to 1404 | 89.51 | 28 | 0 | TOWER 2 - STILT PLUS 16 FLOORS - 3BHK |
| Flat No 1501 to 1504, 1601 to 1604 | 89.51 | 8 | 0 | TOWER 2 - STILT PLUS 16 FLOORS - 3BHK |
| Flat No 101 to 104, 201 to 204, 301 to 304, 401 to 404, 501 to 504, 601 to 604, 701 to 704 | 89.51 | 28 | 0 | TOWER 3 - STILT PLUS 15 FLOORS - 3BHK |
| Flat No 801 to 804, 901 to 904, 1001 to 1004, 1101 to 1104, 1201 to 1204, 1301 to 1304, 1401 to 1404 | 89.51 | 28 | 0 | TOWER 3 - STILT PLUS 15 FLOORS - 3BHK |
| Flat No 1501 to 1504 | 89.51 | 4 | 0 | TOWER 3 - STILT PLUS 15 FLOORS - 3BHK |
| Flat No 101, 102, 201, 202, 301, 302, 401, 402, 501, 502, 601, 602, 701, 702, 801, 802, 901, 902 | 72.54 | 18 | 0 | TOWER 4 - STILT PLUS 10 FLOORS - 2BHK |
| Flat No 1001, 1002 | 72.54 | 2 | 0 | TOWER 4 - STILT PLUS 10 FLOORS - 2BHK |
| Flat No 101 to 103, 201 to 203, 301 to 303, 401 to 403, 501 to 503, 601 to 603, 701 to 703 | 29.57 | 21 | 0 | TOWER 5 - STILT PLUS 7 FLOORS - 1BHK |
| SCO 1 Basement plus Ground | 123.75 | 1 | 0 | COMMERCIAL UNITS |
| SCO 1 First Floor | 61.38 | 1 | 0 | COMMERCIAL UNITS |
| SCO 1 Second Floor | 61.38 | 1 | 0 | COMMERCIAL UNITS |
| SCO 2 Basement plus Ground | 126.95 | 1 | 0 | COMMERCIAL UNITS |
| SCO 2 First Floor | 62.97 | 1 | 0 | COMMERCIAL UNITS |
| SCO 2 Second Floor | 62.97 | 1 | 0 | COMMERCIAL UNITS |
| SCO 3 Basement plus Ground | 120.44 | 1 | 0 | COMMERCIAL UNITS |
| SCO 3 First Floor | 59.71 | 1 | 0 | COMMERCIAL UNITS |
| SCO 3 Second Floor | 59.71 | 1 | 0 | COMMERCIAL UNITS |
| SCO 4 Basement plus Ground | 120.44 | 1 | 0 | COMMERCIAL UNITS |
| SCO 4 First Floor | 59.71 | 1 | 0 | COMMERCIAL UNITS |
| SCO 4 Second Floor | 59.71 | 1 | 0 | COMMERCIAL UNITS |
| SCO 5 Basement plus Ground | 126.95 | 1 | 0 | COMMERCIAL UNITS |
| SCO 5 First Floor | 62.97 | 1 | 0 | COMMERCIAL UNITS |
| SCO 5 Second Floor | 62.97 | 1 | 0 | COMMERCIAL UNITS |
| SCO 6 Basement plus Ground | 123.75 | 1 | 0 | COMMERCIAL UNITS |
| SCO 6 First Floor | 61.38 | 1 | 0 | COMMERCIAL UNITS |
| SCO 6 Second Floor | 61.38 | 1 | 0 | COMMERCIAL UNITS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-06-26 | |
|---|---|---|
| Proposed completion | 2032-06-25 |
Quarterly progress
| Quarter | Filed on | Sold | Booked |
|---|---|---|---|
| 2026-Q3 | 2026-10-14 | 0 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Shaurya Land Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=12815&inPromoter_ID=3744&inPromoterType=12815&inQUProject_ID=6612&inQUProject_DN=QUP2026T20266612&inQUProjectYear=2026&inQUProjectQTR=ThirdQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12815&inPromoter_ID=3744&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-04-22
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2026-06-25
- Environment Clearance certificate/ NOC · 2025-10-24
- License to develop colony or society from Competent Authority
- NOC from Mining Department · 2026-07-13
- Other Document (Access to Road) · 2026-07-01 · Sign in to download
- Other Document (Clarification w.r.t. EC) · 2026-08-04 · Sign in to download
- Other Document (Clarification w.r.t. HT NOC) · 2026-08-04
- Other Document (Forest NOC) · 2026-05-04
- Pollution Clearance from Punjab Pollution Control Board · 2026-07-14
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-04-22
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2026-06-25
- Environment Clearance certificate/ NOC · 2025-10-24
- License to develop colony or society from Competent Authority
- NOC from Mining Department · 2026-07-13
- Other Document (Affidavit for NOC ) · 2026-07-10
- Other Document (Clarification w.r.t. HT NOC) · 2026-08-04
- Other Document (Forest NOC) · 2026-05-04
- Pollution Clearance from Punjab Pollution Control Board · 2026-07-14