Overview
GOLF LINKS (PHASE-II)
LEVITY ENTERPRISES PRIVATE LIMITED · Karnal
Units141
Completion2024-07-15Proposed
Valid to2023-06-30
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 33 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 6 documents · 3 source links |
Registration
Registration
| Promoter | LEVITY ENTERPRISES PRIVATE LIMITED | |
|---|---|---|
| District | Karnal | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-KNL-178-2019 | |
| Valid to | 2023-06-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-07-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No. 74 of 2019 dated 22.07.2019 which is valid upto 21.07.2024. | Town & Country Planning Department | |
| Layout Plan | 2019-07-22 | ||
| Building Plan | |||
| I. LICENSE NO. 74 OF 2019 | 2019-07-22 | ||
| II. APPROVAL OF ZONING PLAN |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,21,24,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹8,94,23,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 141 |
|---|
Unit types
| Plot | 8 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 4 | |
| Plot | 5 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 10 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 48 | |
| Plot | 2 | |
| Plot | 2 | |
| Plot | 7 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 9 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 18 | |
| Plot | 2 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-10-15 | |
|---|---|---|
| Proposed completion | 2024-07-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | LEVITY ENTERPRISES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | KOTAK MAHINDRA BANK LIMITED | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/print_quarterly_schedules/MQ==/Njk0/MjAxOQ==
- https://haryanarera.gov.in/view_project/project_preview_open/825
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-08-21
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-08-21
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-08-21 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-08-21
- Completion Certificate · 2022-04-25 · Sign in to download