Overview
Gomti Ganj
NIRMALA INFRADEVELOPERS LIMITED · Lucknow
Units265
Completion2025-12-31Revised · Proposed 2020-04-30
Registered on2017-08-14
Valid to2025-12-31
Approvals1
Complaints27As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 27 project complaints · 39 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 138 unit types |
| Construction & progress | 3 progress details · 23 quarters · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 70 documents · 30 source links |
Registration
Registration
| Promoter | NIRMALA INFRADEVELOPERS LIMITED | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ11286 | |
| Registered on | 2017-08-14 | |
| Valid to | 2025-12-31 | |
| Project type | Commercial | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2020-04-30 | |
| Revised completion | 2025-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 38139 | 2015-05-14 | 2020-05-13 | Lucknow Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 27 | |
|---|---|---|
| Promoter | 39 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹80,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,000 | |
|---|---|---|
| Towers | 4 | |
| Maximum floors | 7 | |
| Units | 265 |
Unit types
| SHOP | 14.26 | 1 | Cut Out | 2 |
| SHOP | 14.26 | 1 | Cut Out | 3 |
| SHOP | 14.26 | 1 | Cut Out | 4 |
| SHOP | 14.53 | 1 | Cut Out | 1 |
| SHOP | 14.53 | 1 | Cut Out | 2 |
| SHOP | 14.53 | 1 | Cut Out | 3 |
| SHOP | 14.53 | 1 | Cut Out | 4 |
| SHOP | 29.43 | 1 | Cut Out | 5 |
| SHOP | 29.43 | 1 | Cut Out | 6 |
| SHOP | 29.62 | 1 | Cut Out | 5 |
| SHOP | 29.62 | 1 | Cut Out | 6 |
| SHOP | 68.27 | 1 | Circle | 1 |
| SHOP | 68.27 | 1 | Circle | 2 |
| SHOP | 68.27 | 1 | Circle | 3 |
| SHOP | 68.27 | 1 | Circle | 4 |
| SHOP | 68.27 | 1 | Circle | 5 |
| SHOP | 68.27 | 1 | Circle | 6 |
| SHOP | 69.53 | 1 | Circle | 1 |
| SHOP | 69.53 | 1 | Circle | 2 |
| SHOP | 69.53 | 1 | Circle | 3 |
| SHOP | 69.53 | 1 | Circle | 4 |
| SHOP | 69.53 | 1 | Circle | 5 |
| SHOP | 69.53 | 1 | Circle | 6 |
| SHOP | 70.79 | 1 | Circle | GF |
| SHOP | 71.4 | 1 | Circle | GF |
| SHOP | 82.37 | 1 | Circle | GF |
| SHOP | 82.7 | 1 | Circle | GF |
| SHOP | 83.93 | 1 | Circle | 1 |
| SHOP | 83.93 | 1 | Circle | 2 |
| SHOP | 83.93 | 1 | Circle | 5 |
| SHOP | 84.4 | 1 | Circle | 1 |
| SHOP | 84.4 | 1 | Circle | 2 |
| SHOP | 84.4 | 1 | Circle | 5 |
| SHOP | 206.78 | 1 | Circle | 3 |
| SHOP | 11.32 | 1 | A | GF |
| SHOP | 11.34 | 1 | A | GF |
| SHOP | 12.3 | 1 | A | GF |
| SHOP | 27.03 | 8 | A | 6 |
| SHOP | 27.03 | 8 | A | 5 |
| SHOP | 29.65 | 2 | A | GF |
| SHOP | 31.06 | 2 | A | 5 |
| SHOP | 31.06 | 2 | A | 6 |
| SHOP | 31.78 | 4 | A | 5 |
| SHOP | 31.78 | 4 | A | 6 |
| SHOP | 31.83 | 2 | A | 5 |
| SHOP | 31.83 | 2 | A | 6 |
| SHOP | 32.47 | 1 | A | GF |
| SHOP | 32.86 | 2 | A | 5 |
| SHOP | 33.47 | 1 | A | GF |
| SHOP | 32.86 | 2 | A | 6 |
| SHOP | 34.29 | 2 | A | 6 |
| SHOP | 34.29 | 2 | A | 5 |
| SHOP | 34.34 | 2 | A | 5 |
| SHOP | 34.34 | 2 | A | 6 |
| SHOP | 34.35 | 2 | A | 6 |
| SHOP | 34.35 | 2 | A | 5 |
| SHOP | 43.97 | 2 | A | GF |
| SHOP | 45.25 | 1 | A | GF |
| SHOP | 48.05 | 10 | A | 1 |
| SHOP | 48.05 | 10 | A | 2 |
| SHOP | 48.05 | 10 | A | 3 |
| SHOP | 48.05 | 10 | A | 4 |
| SHOP | 51.48 | 1 | A | GF |
| SHOP | 56.61 | 2 | A | 1 |
| SHOP | 56.61 | 2 | A | 2 |
| SHOP | 56.61 | 2 | A | 3 |
| SHOP | 56.61 | 2 | A | 4 |
| SHOP | 61.23 | 2 | A | 1 |
| SHOP | 61.23 | 2 | A | 2 |
| SHOP | 61.23 | 2 | A | 3 |
| SHOP | 61.23 | 2 | A | 4 |
| SHOP | 170.98 | 1 | A | GF |
| SHOP | 195.24 | 1 | A | GF |
| SHOP | 272.8 | 1 | A | GF |
| SHOP | 28.65 | 1 | A | GF |
| SHOP | 10.52 | 1 | B | 5 |
| SHOP | 12.88 | 6 | B | 5 |
| SHOP | 13.12 | 1 | B | 5 |
| SHOP | 13.23 | 2 | B | 5 |
| SHOP | 13.51 | 1 | B | 5 |
| SHOP | 14.14 | 16 | B | 5 |
| SHOP | 14.4 | 1 | B | 5 |
| SHOP | 14.44 | 1 | B | 5 |
| SHOP | 14.56 | 2 | B | 5 |
| SHOP | 14.91 | 4 | B | 5 |
| SHOP | 15.07 | 1 | B | 5 |
| SHOP | 15.09 | 3 | B | 5 |
| SHOP | 16.17 | 1 | B | 5 |
| SHOP | 16.34 | 1 | B | 5 |
| SHOP | 16.8 | 1 | B | 5 |
| SHOP | 17.33 | 1 | B | 5 |
| SHOP | 17.98 | 1 | B | 5 |
| SHOP | 18.42 | 0 | B | 5 |
| SHOP | 31.77 | 1 | B | GF |
| SHOP | 32.77 | 1 | B | GF |
| SHOP | 33.78 | 1 | B | GF |
| SHOP | 37.62 | 1 | B | GF |
| SHOP | 43.35 | 2 | B | 1 |
| SHOP | 43.35 | 2 | B | 2 |
| SHOP | 43.35 | 2 | B | 3 |
| SHOP | 43.35 | 2 | B | 4 |
| SHOP | 43.97 | 1 | B | GF |
| SHOP | 46.2 | 2 | B | 1 |
| SHOP | 46.2 | 2 | B | 2 |
| SHOP | 46.2 | 2 | B | 3 |
| SHOP | 46.2 | 2 | B | 4 |
| SHOP | 48.05 | 4 | B | 1 |
| SHOP | 48.05 | 3 | B | 2 |
| SHOP | 48.05 | 4 | B | 3 |
| SHOP | 48.05 | 4 | B | 4 |
| SHOP | 49.91 | 1 | B | 1 |
| SHOP | 49.91 | 1 | B | 2 |
| SHOP | 49.91 | 1 | B | 3 |
| SHOP | 49.91 | 1 | B | 4 |
| SHOP | 54.06 | 1 | B | 6 |
| SHOP | 54.64 | 1 | B | 2 |
| SHOP | 56.92 | 1 | B | 1 |
| SHOP | 56.92 | 1 | B | 2 |
| SHOP | 56.92 | 1 | B | 3 |
| SHOP | 56.92 | 1 | B | 4 |
| SHOP | 57.33 | 1 | B | 6 |
| SHOP | 63.09 | 3 | B | 6 |
| SHOP | 70.65 | 1 | B | 1 |
| SHOP | 70.65 | 1 | B | 2 |
| SHOP | 70.65 | 1 | B | 3 |
| SHOP | 70.65 | 1 | B | 4 |
| SHOP | 74.88 | 1 | B | 6 |
| SHOP | 80.59 | 1 | B | 6 |
| SHOP | 82.43 | 2 | B | 6 |
| SHOP | 103.52 | 1 | B | 6 |
| SHOP | 48.81 | 1 | B | 6 |
| SHOP | 170.98 | 1 | B | GF |
| SHOP | 177.83 | 1 | B | GF |
| SHOP | 191.13 | 1 | B | GF |
| OTHER | 1,757.66 | 1 | A | 7 |
| OTHER | 1,568.32 | 2 | A | 7 |
| OTHER | 2,409.53 | 1 | B | 7 |
| OTHER | 1,684.49 | 1 | B | 7 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2015-07-01 | |
|---|---|---|
| Proposed completion | 2020-04-30 | |
| Revised completion | 2025-12-31 |
Quarterly progress
| 2020-Q2 | |
| 2020-Q3 | |
| 2020-Q4 | |
| 2021-Q1 | |
| 2021-Q2 | |
| 2021-Q3 | |
| 2021-Q4 | |
| 2022-Q1 | |
| 2022-Q2 | |
| 2022-Q3 | |
| 2022-Q4 | |
| 2023-Q1 | |
| 2023-Q2 | |
| 2023-Q3 | |
| 2023-Q4 | |
| 2024-Q1 | |
| 2024-Q2 | |
| 2024-Q3 | |
| 2024-Q4 | |
| 2025-Q1 | 77.35% |
| 2025-Q2 | 78.92% |
| 2025-Q3 | 81.35% |
| 2025-Q4 | 92.35% |
Extensions
| Valid to | Reason |
|---|---|
| 2020-10-29 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2025-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NIRMALA INFRADEVELOPERS LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Ltd. | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=Yzcdbzdt0KY=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=Sxmi73nmTcOXKjvsvBp5Ug==&PaURJEMAN4=ZL9MNERkNdbvpGq8yiw6Uw==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=Yzcdbzdt0KY=
- Document
- 2020-Q2 CA certificate
- 2020-Q2 Architect certificate
- 2020-Q2 Engineer certificate
- 2020-Q3 CA certificate
- 2020-Q3 Architect certificate
- 2020-Q3 Engineer certificate
- 2020-Q4 CA certificate
- 2020-Q4 Architect certificate
- 2020-Q4 Engineer certificate
- 2021-Q1 CA certificate
- 2021-Q1 Architect certificate
- 2021-Q1 Engineer certificate
- 2021-Q2 CA certificate
- 2021-Q2 Architect certificate
- 2021-Q2 Engineer certificate
- 2021-Q3 CA certificate
- 2021-Q3 Architect certificate
- 2021-Q3 Engineer certificate
- 2021-Q4 CA certificate
- 2021-Q4 Architect certificate
- 2021-Q4 Engineer certificate
- 2022-Q1 CA certificate
- 2022-Q1 Architect certificate
- 2022-Q1 Engineer certificate
- 2022-Q2 CA certificate
- 2022-Q2 Architect certificate
- 2022-Q2 Engineer certificate
- 2022-Q3 CA certificate
- 2022-Q3 Architect certificate
- 2022-Q3 Engineer certificate
- 2022-Q4 CA certificate
- 2022-Q4 Architect certificate
- 2022-Q4 Engineer certificate
- 2023-Q1 CA certificate
- 2023-Q1 Architect certificate
- 2023-Q1 Engineer certificate
- 2023-Q2 CA certificate
- 2023-Q2 Architect certificate
- 2023-Q2 Engineer certificate
- 2023-Q3 CA certificate
- 2023-Q3 Architect certificate
- 2023-Q3 Engineer certificate
- 2023-Q4 CA certificate
- 2023-Q4 Architect certificate
- 2023-Q4 Engineer certificate
- 2024-Q1 CA certificate
- 2024-Q1 Architect certificate
- 2024-Q1 Engineer certificate
- 2024-Q2 CA certificate
- 2024-Q2 Architect certificate
- 2024-Q2 Engineer certificate
- 2024-Q3 CA certificate
- 2024-Q3 Architect certificate
- 2024-Q3 Engineer certificate
- 2024-Q4 CA certificate
- 2024-Q4 Architect certificate
- 2024-Q4 Engineer certificate
- 2025-Q1 CA certificate
- 2025-Q1 Architect certificate
- 2025-Q1 Engineer certificate
- 2025-Q2 CA certificate
- 2025-Q2 Architect certificate
- 2025-Q2 Engineer certificate
- 2025-Q3 CA certificate
- 2025-Q3 Architect certificate
- 2025-Q3 Engineer certificate
- 2025-Q4 CA certificate
- 2025-Q4 Architect certificate
- 2025-Q4 Engineer certificate
- 2020-Q2
- 2020-Q3
- 2020-Q4
- 2021-Q1
- 2021-Q2
- 2021-Q3
- 2021-Q4
- 2022-Q1
- 2022-Q2
- 2022-Q3
- 2022-Q4
- 2023-Q1
- 2023-Q2
- 2023-Q3
- 2023-Q4
- 2024-Q1
- 2024-Q2
- 2024-Q3
- 2024-Q4
- 2025-Q1
- 2025-Q2
- 2025-Q3
- 2025-Q4