Overview
GOOD LUCK RESIDENCY
GOODLUCK GLOBAL PRIVATE LIMITED · RAIPUR
Units302
Booked214 of 302As of 2025-03-31
Construction progress100%As of 2025-03-31
Completion2025-03-30Revised · Proposed 2022-06-30
Registered on2018-07-18
Approvals2
Cases3
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 3 cases |
| Contract & costs | 2 cost heads · 27 quarters |
| Technical report | |
| Site & area | 3 site details · 302 unit types |
| Construction & progress | 4 progress details · 27 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 182 documents · 11 source links |
Registration
Registration
| Promoter | GOODLUCK GLOBAL PRIVATE LIMITED | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA180718000607 | |
| Registered on | 2018-07-18 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2022-06-30 | |
| Revised completion | 2025-03-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2025-03046 | CG RERA | Complaint | Disposed | 2025-11-26 |
| SM-EXP-2024-02516 | CG RERA | Complaint | Disposed | 2024-09-23 |
| M-PRO-2024-02560 | CG RERA | Complaint | Disposed | 2024-09-18 |
Complaints & cases
| Cases | 3 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹42,43,70,000 | |
|---|---|---|
| Construction | ₹17,97,80,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹6,69,300 |
| 2019-Q1 | ₹4,56,649 |
| 2019-Q2 | ₹359 |
| 2019-Q3 | ₹9,11,464 |
| 2019-Q4 | ₹1.24 |
| 2020-Q1 | ₹70,770 |
| 2020-Q2 | ₹70,700 |
| 2020-Q3 | ₹36,686 |
| 2020-Q4 | ₹78 |
| 2021-Q1 | ₹56,195 |
| 2021-Q2 | ₹2,94,358 |
| 2021-Q3 | ₹602 |
| 2021-Q4 | ₹66,787 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹3,78,276 |
| 2022-Q3 | ₹15,81,300 |
| 2022-Q4 | ₹213 |
| 2023-Q1 | ₹214 |
| 2023-Q2 | ₹820 |
| 2023-Q3 | ₹819 |
| 2023-Q4 | ₹819 |
| 2024-Q1 | ₹821 |
| 2024-Q2 | ₹819 |
| 2024-Q3 | ₹1,07,920 |
| 2024-Q4 | ₹821 |
| 2025-Q1 | ₹34,34,321 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 302 | |
|---|---|---|
| Booked | 214 | |
| Booked as of | 2025-03-31 |
Unit types
| A-139 | 1 | 1 |
| A-149 | 1 | 1 |
| A-150 | 1 | 1 |
| A-155 | 1 | 1 |
| A-156 | 1 | 1 |
| A-157 | 1 | 1 |
| A-159 | 1 | 1 |
| A-160 | 1 | 1 |
| A-161 | 1 | 1 |
| A-162 | 1 | 1 |
| A-163 | 1 | 1 |
| A-164 | 1 | 1 |
| A-165 | 1 | 1 |
| A-166 | 1 | 1 |
| A-171 | 1 | 1 |
| A-172 | 1 | 1 |
| A-173 | 1 | 1 |
| A-174 | 1 | 1 |
| A-175 | 1 | 1 |
| A-185 | 1 | 1 |
| A-189 | 1 | 1 |
| A-190 | 1 | 1 |
| A-191 | 1 | 1 |
| A-192 | 1 | 1 |
| A-193 | 1 | 1 |
| A-194 | 1 | 1 |
| A-195 | 1 | 1 |
| A-196 | 1 | 1 |
| A-197 | 1 | 1 |
| A-198 | 1 | 1 |
| A-200 | 1 | 1 |
| A-201 | 1 | 1 |
| A-202 | 1 | 1 |
| A-203 | 1 | 1 |
| A-208 | 1 | 1 |
| A-209 | 1 | 1 |
| A-210 | 1 | 1 |
| A-211 | 1 | 1 |
| A-212 | 1 | 1 |
| A-213 | 1 | 1 |
| A-214 | 1 | 1 |
| A-215 | 1 | 1 |
| A-216 | 1 | 1 |
| A-217 | 1 | 1 |
| A-218 | 1 | 1 |
| A-219 | 1 | 1 |
| A-220 | 1 | 1 |
| A-221 | 1 | 1 |
| A-222 | 1 | 1 |
| A-223 | 1 | 1 |
| A-224 | 1 | 1 |
| A-225 | 1 | 1 |
| A-227 | 1 | 1 |
| A-228 | 1 | 1 |
| A-230 | 1 | 1 |
| A-233 | 1 | 1 |
| A-235 | 1 | 1 |
| A-238 | 1 | 1 |
| A-240 | 1 | 1 |
| A-241 | 1 | 1 |
| A-242 | 1 | 1 |
| A-243 | 1 | 1 |
| A-148 | 1 | 1 |
| A-204 | 1 | 1 |
| A-237 | 1 | 1 |
| A-226 | 1 | 1 |
| A-229 | 1 | 1 |
| A-177 | 1 | 1 |
| A-184 | 1 | 1 |
| A-143 | 1 | 1 |
| A-231 | 1 | 1 |
| A-181 | 1 | 1 |
| A-205 | 1 | 1 |
| A-206 | 1 | 1 |
| A-207 | 1 | 1 |
| A-178 | 1 | 1 |
| A-234 | 1 | 1 |
| B-B-63 | 1 | 1 |
| B-B-64 | 1 | 1 |
| A-176 | 1 | 1 |
| A-141 | 1 | 1 |
| A-186 | 1 | 1 |
| A-182 | 1 | 1 |
| A-180 | 1 | 1 |
| A-147 | 1 | 1 |
| A-145 | 1 | 1 |
| A-151 | 1 | 1 |
| A-152 | 1 | 1 |
| A-140 | 1 | 1 |
| A-183 | 1 | 1 |
| A-142 | 1 | 1 |
| A-169 | 1 | 1 |
| A-245 | 1 | 1 |
| A-168 | 1 | 1 |
| A-146 | 1 | 1 |
| A-167 | 1 | 1 |
| A-154 | 1 | 1 |
| A-246 | 1 | 1 |
| A-153 | 1 | 1 |
| A-179 | 1 | 1 |
| A-244 | 1 | 1 |
| A-187 | 1 | 1 |
| A-170 | 1 | 1 |
| A-232 | 1 | 1 |
| A-239 | 1 | 1 |
| A-199 | 1 | 1 |
| A-188 | 1 | 1 |
| A-158 | 1 | 1 |
| B-48 | 1 | 1 |
| B-44 | 1 | 1 |
| B-176 | 1 | 1 |
| B-39 | 1 | 1 |
| B-51 | 1 | 1 |
| B-100 | 1 | 1 |
| B-45 | 1 | 1 |
| B-103 | 1 | 1 |
| B-78 | 1 | 1 |
| B-144 | 1 | 1 |
| B-130 | 1 | 1 |
| B-42 | 1 | 1 |
| B-52 | 1 | 1 |
| B-79 | 1 | 1 |
| B-80 | 1 | 1 |
| B-97 | 1 | 1 |
| B-98 | 1 | 1 |
| B-46 | 1 | 1 |
| B-129 | 1 | 1 |
| B-99 | 1 | 1 |
| B-101 | 1 | 1 |
| B-150 | 1 | 1 |
| B-104 | 1 | 1 |
| B-50 | 1 | 1 |
| B-148 | 1 | 1 |
| B-91 | 1 | 1 |
| B-95 | 1 | 1 |
| B-89 | 1 | 1 |
| B-90 | 1 | 1 |
| B-49 | 1 | 1 |
| B-102 | 1 | 1 |
| B-92 | 1 | 1 |
| B-47 | 1 | 1 |
| B-41 | 1 | 1 |
| B-149 | 1 | 1 |
| B-94 | 1 | 1 |
| B-147 | 1 | 1 |
| B-81 | 1 | 1 |
| B-93 | 1 | 1 |
| B-84 | 1 | 1 |
| B-85 | 1 | 1 |
| B-82 | 1 | 1 |
| B-83 | 1 | 1 |
| B-145 | 1 | 1 |
| B-131 | 1 | 1 |
| B-146 | 1 | 1 |
| B-132 | 1 | 1 |
| B-40 | 1 | 1 |
| B-133 | 1 | 1 |
| B-138 | 1 | 1 |
| B-182 | 1 | 1 |
| B-175 | 1 | 1 |
| B-179 | 1 | 1 |
| B-134 | 1 | 1 |
| B-96 | 1 | 1 |
| B-87 | 1 | 1 |
| B-140 | 1 | 1 |
| B-181 | 1 | 1 |
| B-77 | 1 | 1 |
| B-142 | 1 | 1 |
| B-86 | 1 | 1 |
| B-143 | 1 | 1 |
| B-154 | 1 | 1 |
| B-136 | 1 | 1 |
| B-137 | 1 | 1 |
| B-174 | 1 | 1 |
| B-161 | 1 | 1 |
| B-160 | 1 | 1 |
| B-164 | 1 | 1 |
| B-165 | 1 | 1 |
| B-173 | 1 | 1 |
| B-158 | 1 | 1 |
| B-162 | 1 | 1 |
| B-155 | 1 | 1 |
| B-156 | 1 | 1 |
| B-163 | 1 | 1 |
| B-166 | 1 | 1 |
| B-172 | 1 | 1 |
| B-159 | 1 | 1 |
| B-170 | 1 | 1 |
| B-167 | 1 | 1 |
| B-168 | 1 | 1 |
| B-135 | 1 | 1 |
| B-169 | 1 | 1 |
| B-152 | 1 | 1 |
| B-153 | 1 | 1 |
| B-151 | 1 | 1 |
| B-171 | 1 | 1 |
| B-88 | 1 | 1 |
| B-139 | 1 | 1 |
| B-157 | 1 | 1 |
| B-141 | 1 | 1 |
| B-177 | 1 | 1 |
| B-180 | 1 | 1 |
| B-18 | 1 | 1 |
| B-8 | 1 | 0 |
| B-9 | 1 | 0 |
| B-10 | 1 | 0 |
| B-11 | 1 | 0 |
| B-12 | 1 | 0 |
| B-13 | 1 | 0 |
| B-14 | 1 | 0 |
| B-15 | 1 | 0 |
| B-16 | 1 | 0 |
| B-17 | 1 | 0 |
| B-19 | 1 | 0 |
| B-20 | 1 | 0 |
| B-21 | 1 | 1 |
| B-22 | 1 | 0 |
| B-23 | 1 | 0 |
| B-24 | 1 | 1 |
| B-25 | 1 | 0 |
| B-26 | 1 | 1 |
| B-27 | 1 | 1 |
| B-28 | 1 | 1 |
| B-29 | 1 | 1 |
| B-30 | 1 | 1 |
| B-1 | 1 | 0 |
| B-2 | 1 | 0 |
| B-3 | 1 | 0 |
| B-4 | 1 | 0 |
| B-5 | 1 | 0 |
| B-6 | 1 | 0 |
| B-7 | 1 | 0 |
| B-32 | 1 | 0 |
| B-33 | 1 | 0 |
| B-34 | 1 | 0 |
| B-35 | 1 | 0 |
| B-36 | 1 | 0 |
| B-37 | 1 | 0 |
| B-38 | 1 | 0 |
| B-53 | 1 | 0 |
| B-54 | 1 | 0 |
| B-55 | 1 | 0 |
| B-56 | 1 | 0 |
| B-57 | 1 | 0 |
| B-59 | 1 | 0 |
| B-60 | 1 | 0 |
| B-61 | 1 | 0 |
| B-62 | 1 | 0 |
| B-65 | 1 | 0 |
| B-66 | 1 | 0 |
| B-67 | 1 | 0 |
| B-68 | 1 | 0 |
| B-69 | 1 | 0 |
| B-70 | 1 | 0 |
| B-71 | 1 | 0 |
| B-72 | 1 | 0 |
| B-73 | 1 | 0 |
| B-74 | 1 | 0 |
| B-75 | 1 | 0 |
| B-76 | 1 | 0 |
| B-105 | 1 | 0 |
| B-106 | 1 | 0 |
| B-107 | 1 | 0 |
| B-108 | 1 | 0 |
| B-109 | 1 | 0 |
| B-110 | 1 | 0 |
| B-111 | 1 | 0 |
| B-112 | 1 | 0 |
| B-113 | 1 | 0 |
| B-114 | 1 | 0 |
| B-115 | 1 | 0 |
| B-116 | 1 | 0 |
| B-117 | 1 | 0 |
| B-118 | 1 | 0 |
| B-119 | 1 | 0 |
| B-120 | 1 | 0 |
| B-121 | 1 | 0 |
| B-122 | 1 | 0 |
| B-123 | 1 | 0 |
| B-124 | 1 | 0 |
| B-125 | 1 | 0 |
| B-126 | 1 | 0 |
| B-127 | 1 | 0 |
| B-128 | 1 | 0 |
| B-183 | 1 | 0 |
| B-184 | 1 | 0 |
| B-185 | 1 | 0 |
| B-186 | 1 | 0 |
| B-187 | 1 | 0 |
| B-188 | 1 | 0 |
| B-189 | 1 | 0 |
| B-190 | 1 | 0 |
| B-191 | 1 | 0 |
| B-192 | 1 | 0 |
| B-193 | 1 | 0 |
| B-194 | 1 | 0 |
| a-144 | 1 | 1 |
| b-43 | 1 | 1 |
| b-178 | 1 | 1 |
| a-236 | 1 | 1 |
| b-31 | 1 | 0 |
| b-58 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-03-31 | |
| Proposed completion | 2022-06-30 | |
| Revised completion | 2025-03-30 |
Quarterly progress
| 2018-Q3 | 0% |
| 2018-Q4 | 26% |
| 2019-Q1 | 29% |
| 2019-Q2 | 45% |
| 2019-Q3 | 49% |
| 2019-Q4 | 49% |
| 2020-Q1 | 58% |
| 2020-Q2 | 59% |
| 2020-Q3 | 60% |
| 2020-Q4 | 61% |
| 2021-Q1 | 64% |
| 2021-Q2 | 66% |
| 2021-Q3 | 70% |
| 2021-Q4 | 73% |
| 2022-Q1 | 80% |
| 2022-Q2 | 85% |
| 2022-Q3 | 90% |
| 2022-Q4 | 92% |
| 2023-Q1 | 95% |
| 2023-Q2 | 96% |
| 2023-Q3 | 97% |
| 2023-Q4 | 98% |
| 2024-Q1 | 98% |
| 2024-Q2 | 98% |
| 2024-Q3 | 98% |
| 2024-Q4 | 99% |
| 2025-Q1 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GOODLUCK GLOBAL PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=Njky
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Modified Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2025-11-26 · Sign in to download
- Final order · 2024-09-23 · Sign in to download
- Final order · 2024-09-18 · Sign in to download
- Interim order · 2024-08-30 · Sign in to download
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- SM-EXP-2025-03046 · Sign in to download
- SM-EXP-2024-02516 · Sign in to download
- M-PRO-2024-02560 · Sign in to download