Overview
GOVERDHAN VATIKA BLOCK-A
RAJESH BALAI · Jaipur
Units72
Booked31 of 72As of 2025-06-30
Completion2025-07-31Revised · Proposed 2023-07-10
Registered on2023-10-06
Valid to2025-07-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 41 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 59 documents · 6 source links |
Registration
Registration
| Promoter | RAJESH BALAI | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2023/2740 | |
| Registered on | 2023-10-06 | |
| Valid to | 2025-07-31 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2023-07-10 | |
| Revised completion | 2025-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,50,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹3,15,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2025-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 10,778.71 | |
|---|---|---|
| Built-up (m²) | 6,957 | |
| Towers | 72 | |
| Units | 72 | |
| Booked | 31 | |
| Booked as of | 2025-06-30 |
Unit types
| Plot No. 1 | 1 | 0 |
| Plot No. 2 | 1 | 0 |
| Plot No. 3 | 1 | 0 |
| Plot No. 4 | 1 | 0 |
| Plot No. 5 | 1 | 0 |
| Plot No. 6 | 1 | 0 |
| Plot No. 7 | 1 | 0 |
| Plot No. 8 | 1 | 0 |
| Plot No. 9 to 16, 34 to 39, 42 to 47 | 20 | 0 |
| Plot No. 17 | 1 | 0 |
| Plot No. 18 | 1 | 0 |
| Plot No. 19 | 1 | 0 |
| Plot No. 20 | 1 | 0 |
| Plot No. 21 | 1 | 0 |
| Plot No. 22 | 1 | 0 |
| Plot No. 23 | 1 | 0 |
| Plot No. 24 | 1 | 0 |
| Plot No. 25 | 1 | 0 |
| Plot No. 26 | 1 | 0 |
| Plot No. 27 | 1 | 0 |
| Plot No. 28 | 1 | 0 |
| Plot No. 29 | 1 | 0 |
| Plot No. 30 | 1 | 0 |
| Plot No. 31 | 1 | 0 |
| Plot No. 32 | 1 | 0 |
| Plot No. 33 & 48 | 2 | 0 |
| Plot No. 40 & 41 | 2 | 0 |
| Plot No. 49 | 1 | 0 |
| Plot No. 50 | 1 | 0 |
| Plot No. 51 | 1 | 0 |
| Plot No. 52 | 1 | 0 |
| Plot No. 53 | 1 | 0 |
| Plot No. 54 | 1 | 0 |
| Plot No. 55 | 1 | 0 |
| Plot No. 56 | 1 | 0 |
| Plot No. 57 | 1 | 0 |
| Plot No. 58 | 1 | 0 |
| Plot No. 59 | 1 | 0 |
| Plot No. 60 to 70 | 11 | 0 |
| Plot No. 71 | 1 | 0 |
| Informal Commercial Plot | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-07-10 | |
|---|---|---|
| Proposed completion | 2023-07-10 | |
| Revised completion | 2025-07-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2025-Q2 | 2025-07-30 | 31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAJESH BALAI | |
|---|---|---|
| Type | Individual | |
| Escrow bank | PUNJAB & SIND BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=l9CS-vj9C-ntavexs1L7jQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/l9CS-vj9C-ntavexs1L7jQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=l9CS%2Bvj9C%2Bntavexs1L7jQ%3D%3D&QuarterIdEnc=kw5%2Fn2KiUmwNiFAAJ3zlcA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=ooZSiI91wAI%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Document
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- SitePlanPath · 2023-08-29
- Site_Plan_Doc_Sanctioned
- R1_UploadDoc · 2025-05-22 · Sign in to download
- R2_UploadDoc · 2025-05-22 · Sign in to download
- R3_UploadedPath · 2025-07-10 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download