Overview
GOVIND BAGH-DIAMOND
GOVIND KRIPA INFRA PROJECTS LLP · Jaipur
Units126
Booked8 of 126As of 2023-03-31
Completion2025-07-14Revised · Proposed 2022-07-14
Registered on2022-07-26
Valid to2025-07-14
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 33 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 48 documents · 6 source links |
Registration
Registration
| Promoter | GOVIND KRIPA INFRA PROJECTS LLP | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2022/2076 | |
| Registered on | 2022-07-26 | |
| Valid to | 2025-07-14 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2022-07-14 | |
| Revised completion | 2025-07-14 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,89,53,448 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹12,03,90,278 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2023-Q1 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 19,910 | |
|---|---|---|
| Built-up (m²) | 11,025.84 | |
| Towers | 126 | |
| Units | 126 | |
| Booked | 8 | |
| Booked as of | 2023-03-31 |
Unit types
| Plot No. 1 | 1 | 0 |
| Plot No. 2, 4, 5, 8 to 13, 19 to 20, 57 to 63 | 18 | 0 |
| Plot No. 30 to 37, 56 | 9 | 0 |
| Plot No. 3 | 1 | 0 |
| Plot No. 6 | 1 | 0 |
| Plot No. 7 | 1 | 0 |
| Plot No. 14 to 16, 21 to 22, 40 to 45, 48 to 54, 66 to 73, 84 to 90 | 32 | 0 |
| Plot No. 38, 39, 55, 73, 91 | 5 | 0 |
| Plot No. 17 | 1 | 0 |
| Plot No. 18 | 1 | 0 |
| Plot No. 23 | 1 | 0 |
| Plot No. 24 | 1 | 0 |
| Plot No. 25 | 1 | 0 |
| Plot No. 26 | 1 | 0 |
| Plot No. 27 | 1 | 0 |
| Plot No. 28 | 1 | 0 |
| Plot No. 29 | 1 | 0 |
| Plot No. 46 | 1 | 0 |
| Plot No. 47 | 1 | 0 |
| Plot No. 64 | 1 | 0 |
| Plot No. 65 | 1 | 0 |
| Plot No. 75 to 81 | 7 | 0 |
| Plot No. 74 | 1 | 0 |
| Plot No. 82 | 1 | 0 |
| Plot No. 83 | 1 | 0 |
| Plot No. 92 to 95 | 4 | 0 |
| Plot No. 96 | 1 | 0 |
| Plot No. S-1 to S-3, S-18 to S-20 | 6 | 0 |
| Plot No. S-4 to S-17 | 14 | 0 |
| JDA Commercial Plot No. C-1 | 1 | 0 |
| Khatedar Commercial Plot No. C-2 to C-6 | 5 | 0 |
| JDA Commercial Plot No. C-7 to C-9 | 3 | 0 |
| JDA Commercial Plot No. C-10 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-07-14 | |
|---|---|---|
| Proposed completion | 2022-07-14 | |
| Revised completion | 2025-07-14 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2023-Q1 | 2023-04-28 | 8 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GOVIND KRIPA INFRA PROJECTS LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 7 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=I8zzWy-HwH2o0mnqZfzW0Q
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/I8zzWy-HwH2o0mnqZfzW0Q
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=I8zzWy%2BHwH2o0mnqZfzW0Q%3D%3D&QuarterIdEnc=0dVTidllfdsvgxIT%2FflOsw%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=Qdb8wt8NfyY%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2022-07-18
- Copy Of Approved Site Plan
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Others
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- Site_Plan_Doc_Sanctioned
- SitePlanPath · 2022-07-15
- SitePlanPath · 2022-07-15
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · Sign in to download
- R2_UploadDoc · Sign in to download
- R3_UploadedPath · Sign in to download