GOVIND BAGH-EMERALD

GOVIND KRIPA INFRA PROJECTS LLP · Jaipur
Units104
Booked59 of 104As of 2023-03-31
Completion2025-10-19Revised · Proposed 2022-10-19
Registered on2022-10-23
Valid to2025-10-19

Sections

Property title & search report
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area6 site details · 24 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details
The evidence
Sources39 documents · 6 source links

Registration

Registration

PromoterGOVIND KRIPA INFRA PROJECTS LLP
DistrictJaipur
RegulatorRajasthan RERA
Registration numberRAJ/P/2022/2223
Registered on2022-10-23
Valid to2025-10-19
Project typePlotted
Status (as filed)COMPLETED
Proposed completion2022-10-19
Revised completion2025-10-19