Overview
Govind Gopal Heritage
Vindhywasini Engicon Pvt. Ltd. · Patna
Units26
Booked5 of 26As of 2025-06-30
Construction progress100%As of 2025-06-30
Completion2024-08-01Proposed
Registered on2019-11-22
Valid to2024-08-01
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 15 unit types |
| Construction & progress | 4 progress details · 22 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 36 documents · 28 source links |
Registration
Registration
| Promoter | Vindhywasini Engicon Pvt. Ltd. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP93815-1/1106/R-843/2019 | |
| Registered on | 2019-11-22 | |
| Valid to | 2024-08-01 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2024-08-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) | |
| Notice of Commencement | |
| Fire NOC | Office of the State Fire Officer-Cum-Director, Patna, Bihar |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,079.6 | |
|---|---|---|
| Built-up (m²) | 2,072.38 | |
| FAR | 1.92 | |
| Towers | 1 | |
| Units | 26 | |
| Booked | 5 | |
| Booked as of | 2025-06-30 |
Unit types
| 2 BHK | 2 | Govind Gopal Heritage |
| 3 BHK | 2 | Govind Gopal Heritage |
| 2 BHK | 2 | Govind Gopal Heritage |
| 3 BHK | 2 | Govind Gopal Heritage |
| 2 BHK | 2 | Govind Gopal Heritage |
| 2 BHK | 2 | Govind Gopal Heritage |
| 2 BHK | 2 | Govind Gopal Heritage |
| 2 BHK | 2 | Govind Gopal Heritage |
| 3 BHK | 2 | Govind Gopal Heritage |
| 4 BHK | 2 | Govind Gopal Heritage |
| Office | 2 | Govind Gopal Heritage |
| Shop | 1 | Govind Gopal Heritage |
| Shop | 1 | Govind Gopal Heritage |
| Shop | 1 | Govind Gopal Heritage |
| Shop | 1 | Govind Gopal Heritage |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-06-30 | |
| Start | 2019-11-06 | |
| Proposed completion | 2024-08-01 |
Quarterly progress
| 2025-Q2 | 2025-08-20 | 100% | 5 |
| 2025-Q1 | 2025-04-14 | ||
| 2024-Q4 | 2025-01-15 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-07-16 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-21 | ||
| 2022-Q4 | 2023-04-21 | ||
| 2022-Q3 | 2023-04-21 | ||
| 2022-Q2 | 2022-08-03 | ||
| 2022-Q1 | 2022-07-26 | ||
| 2021-Q4 | 2022-07-26 | ||
| 2021-Q3 | 2022-07-26 | ||
| 2021-Q2 | 2022-07-26 | ||
| 2021-Q1 | 2022-07-26 | ||
| 2020-Q4 | 2022-07-26 | ||
| 2020-Q3 | 2021-01-29 | ||
| 2020-Q2 | 2021-01-29 | ||
| 2020-Q1 | 2021-01-28 | ||
| 2019-Q4 | 2020-02-05 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Vindhywasini Engicon Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP09272019193815-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP09272019193815&ld=pan&pj=RERAP09272019193815-1&f=2025-2026&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP09272019193815-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-20
- Q4-Jan to Mar / 2024-2025 · 2025-04-14
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-16
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-21
- Q3-Oct to Dec / 2022-2023 · 2023-04-21
- Q2-Jul to Sep / 2022-2023 · 2023-04-21
- Q1-Apr to Jun / 2022-2023 · 2022-08-03
- Q4-Jan to Mar / 2021-2022 · 2022-07-26
- Q3-Oct to Dec / 2021-2022 · 2022-07-26
- Q2-Jul to Sep / 2021-2022 · 2022-07-26
- Q1-Apr to Jun / 2021-2022 · 2022-07-26
- Q4-Jan to Mar / 2020-2021 · 2022-07-26
- Q3-Oct to Dec / 2020-2021 · 2022-07-26
- Q2-Jul to Sep / 2020-2021 · 2021-01-29
- Q1-Apr to Jun / 2020-2021 · 2021-01-29
- Q4-Jan to Mar / 2019-2020 · 2021-01-28
- Q3-Oct to Dec / 2019-2020 · 2020-02-05
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2025-Q1 · 2025-04-14
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-16
- 2024-Q1 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-21
- 2022-Q4 · 2023-04-21
- 2022-Q3 · 2023-04-21
- 2022-Q2 · 2022-08-03
- 2022-Q1 · 2022-07-26
- 2021-Q4 · 2022-07-26
- 2021-Q3 · 2022-07-26
- 2021-Q2 · 2022-07-26
- 2021-Q1 · 2022-07-26
- 2020-Q4 · 2022-07-26
- 2020-Q3 · 2021-01-29
- 2020-Q2 · 2021-01-29
- 2020-Q1 · 2021-01-28
- 2019-Q4 · 2020-02-05