Overview
GREEN BHOOMI
BST DEVELOPERS INDIA PVT LTD · Gurugram
Units96
Completion2027-01-25Proposed
Registered on2023-01-16
Valid to2027-01-25
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 14 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 3 source links |
Registration
Registration
| Promoter | BST DEVELOPERS INDIA PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/669/401/2023/13 DATED 16.01.2023 | |
| Registered on | 2023-01-16 | |
| Valid to | 2027-01-25 | |
| Status (as filed) | Registered | |
| Proposed completion | 2027-01-25 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 170 of 2022(22.10.2022) | Town & Country Planning Department | |
| Layout Plan | 2022-10-27 | ||
| Building Plan | |||
| I. LICENSE | 2022-10-27 | ||
| II. LAYOUT PLAN | 2022-10-27 | ||
| III. SERVICE PLAN ESTIMATES FROM GMDA | 2022-11-23 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹28,68,51,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹49,15,78,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 22,814.962 | |
|---|---|---|
| FAR | 1 | |
| Units | 96 |
Unit types
| Plot | 22 | |
| Plot | 33 | |
| Plot | 10 | |
| Plot | 2 | |
| Plot | 10 | |
| Plot | 12 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-01-26 | |
|---|---|---|
| Proposed completion | 2027-01-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BST DEVELOPERS INDIA PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LTD | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2207
- https://nominatim.openstreetmap.org/search?q=sector+99a%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2023-01-16
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2022-12-01 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2022-12-01
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2022-12-01
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2022-12-01
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2022-12-01
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2022-12-01
- DEMARCATION PLAN · 2022-12-14
- ZONING PLAN · 2022-12-14
- NO LOAN CERTIFICATE · 2023-08-18 · Sign in to download
- SIZRA · 2023-08-18 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2023-08-18 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2023-08-18 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2023-08-18 · Sign in to download
- CA CERTIFICATE LAND COST ANNEXURE-5 · 2023-08-18 · Sign in to download
- ELECTRICAL LOAD INTIMATION LETTER · 2023-08-18 · Sign in to download
- JAMABANDI · 2023-08-18 · Sign in to download
- LAYOUT PLAN · 2023-08-18
- PL-DDJAY BST EXTERNAL SITE PLAN-R1 SEWER LINE · 2023-08-18
- PL-UNDER GROUND WATER TANK DETAIL FOR APPROVAL -18-03-2023-MODEL · 2023-08-18
- PL-DDJAY BST EXTERNAL SITE PLAN-R1 STORM LINE · 2023-08-18
- PL-UNDER GROUND WATER TANK STRU.DETAIL · 2023-08-18 · Sign in to download
- PROMOTER AFFIDAVIT REGARDING BANK ACCOUNT · 2023-08-18 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2023-08-18 · Sign in to download
- Completion Certificate · 2026-03-20 · Sign in to download