Overview
Green Lotus Avenue
Barnala Developers · Sahibzada Ajit Singh Nagar (Mohali)
Units235
Completion2019-12-31Proposed
Valid to2018-12-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 9 unit types |
| Construction & progress | 2 progress details · 33 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 27 documents · 46 source links |
Registration
Registration
| Promoter | Barnala Developers | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0072 | |
| Valid to | 2018-12-31 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2019-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| Electric Substation NOC | 2017-12-04 |
| Environment Clearance certificate/ NOC | 2015-05-28 |
| License as Promoter from competent Authority | 2015-01-08 |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2015-06-09 |
| NOC from Mining Department | 2017-06-19 |
| Other Document (Structure Safty NOC) | 2018-05-02 |
| Other Document (Wild Clearance NOC) | 2016-01-04 |
| Pollution Clearance from Punjab Pollution Control Board | 2018-11-21 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹98,30,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 14,386.575 | |
|---|---|---|
| Towers | 5 | |
| Maximum floors | 14 | |
| Units | 235 |
Unit types
| 3+1 BHK | 118.21 | 25 | TOWER A |
| 3 BHK | 93.92 | 25 | TOWER A |
| 4 BHK | 147.37 | 27 | TOWER B |
| 5 BHK | 176.22 | 26 | TOWER B |
| 3BHK | 93.92 | 26 | TOWER C |
| 3+1 BHK | 118.25 | 27 | TOWER C |
| 1 BHK | 36.25 | 41 | TOWER D |
| 2 BHK | 76.76 | 28 | TOWER D |
| 3 BHK | 104.35 | 10 | TOWER E |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2015-03-16 | |
|---|---|---|
| Proposed completion | 2019-12-31 |
Quarterly progress
| 2021-Q1 | 2021-08-14 |
| 2018-Q1 | 2021-09-14 |
| 2018-Q2 | 2021-09-14 |
| 2018-Q3 | 2021-09-14 |
| 2018-Q4 | 2021-09-14 |
| 2019-Q1 | 2021-09-14 |
| 2019-Q2 | 2021-09-14 |
| 2019-Q3 | 2021-09-14 |
| 2019-Q4 | 2021-09-14 |
| 2020-Q1 | 2021-09-16 |
| 2020-Q2 | 2021-09-16 |
| 2020-Q3 | 2021-09-19 |
| 2020-Q4 | 2021-09-19 |
| 2021-Q2 | 2021-09-19 |
| 2021-Q3 | 2022-02-15 |
| 2021-Q4 | 2022-02-26 |
| 2022-Q1 | 2022-04-15 |
| 2022-Q2 | 2022-08-03 |
| 2022-Q3 | 2022-11-21 |
| 2022-Q4 | 2023-01-16 |
| 2023-Q1 | 2023-04-13 |
| 2023-Q2 | 2023-07-15 |
| 2023-Q3 | 2023-10-19 |
| 2023-Q4 | 2024-03-14 |
| 2024-Q1 | 2024-06-17 |
| 2024-Q2 | 2024-11-10 |
| 2024-Q3 | 2024-11-10 |
| 2025-Q1 | 2025-05-18 |
| 2025-Q2 | 2025-08-13 |
| 2025-Q3 | 2026-09-03 |
| 2025-Q4 | 2026-09-03 |
| 2026-Q1 | 2026-09-03 |
| 2026-Q2 | 2026-09-03 |
Extensions
| Valid to |
|---|
| 2019-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Barnala Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | United Bank of India | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Contractor | DCS STRUCTURE COMPANY |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10419&inPromoter_ID=1355&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2015-06-09
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2018-04-12 · Sign in to download
- Borewell Registration certificate from Central Ground Water Authority · 2016-04-01
- Building Permit Issue from Municipal Authority · 2015-03-16 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2017-12-04
- Environment Clearance certificate/ NOC · 2015-05-28
- License as Promoter from competent Authority · 2015-01-08
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2015-06-09
- NOC from Mining Department · 2017-06-19
- Other Document (Sewerage Connection) · 2015-01-13 · Sign in to download
- Other Document (Structure Safty NOC) · 2018-05-02
- Other Document (Waste Material and Garbage) · 2015-01-13 · Sign in to download
- Other Document (Wild Clearance NOC) · 2016-01-04
- Pollution Clearance from Punjab Pollution Control Board · 2018-11-21
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2017-12-04
- Environment Clearance certificate/ NOC · 2015-05-28
- License as Promoter from competent Authority · 2015-01-08
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2015-06-09
- NOC from Mining Department · 2017-06-19
- Other Document (Structure Safty NOC) · 2018-05-02
- Other Document (Wild Clearance NOC) · 2016-01-04
- Pollution Clearance from Punjab Pollution Control Board · 2018-11-21
- Extension order · Sign in to download
- 2021-Q1 · 2021-08-14
- 2018-Q1 · 2021-09-14
- 2018-Q2 · 2021-09-14
- 2018-Q3 · 2021-09-14
- 2018-Q4 · 2021-09-14
- 2019-Q1 · 2021-09-14
- 2019-Q2 · 2021-09-14
- 2019-Q3 · 2021-09-14
- 2019-Q4 · 2021-09-14
- 2020-Q1 · 2021-09-16
- 2020-Q2 · 2021-09-16
- 2020-Q3 · 2021-09-19
- 2020-Q4 · 2021-09-19
- 2021-Q2 · 2021-09-19
- 2021-Q3 · 2022-02-15
- 2021-Q4 · 2022-02-26
- 2022-Q1 · 2022-04-15
- 2022-Q2 · 2022-08-03
- 2022-Q3 · 2022-11-21
- 2022-Q4 · 2023-01-16
- 2023-Q1 · 2023-04-13
- 2023-Q2 · 2023-07-15
- 2023-Q3 · 2023-10-19
- 2023-Q4 · 2024-03-14
- 2024-Q1 · 2024-06-17
- 2024-Q2 · 2024-11-10
- 2024-Q3 · 2024-11-10
- 2025-Q1 · 2025-05-18
- 2025-Q2 · 2025-08-13
- 2025-Q3 · 2026-09-03
- 2025-Q4 · 2026-09-03
- 2026-Q1 · 2026-09-03
- 2026-Q2 · 2026-09-03