Overview
GREEN LOTUS SAKSHAM COMMERCIAL
MAYA BUILDERS · Sahibzada Ajit Singh Nagar (Mohali)
Units78
Completion2023-06-30Proposed
Valid to2023-06-30
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 20 unit types |
| Construction & progress | 2 progress details · 21 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 30 source links |
Registration
Registration
| Promoter | MAYA BUILDERS | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PC0122 | |
| Valid to | 2023-06-30 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2017-06-21 |
| CLU Certificate | |
| License as Promoter from competent Authority | 2019-11-15 |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2019-09-17 |
| Other Document (ISSU OF LICENCE COMMERCIAL) | 2020-01-24 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹25,12,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,301.88 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 5 | |
| Units | 78 |
Unit types
| Lower ground floor | 66.26 | 1 | SHOWROOM FLOORS |
| Upper ground floor | 56.97 | 3 | SHOWROOM FLOORS |
| Upper ground floor | 66.91 | 5 | SHOWROOM FLOORS |
| Upper ground floor | 67.47 | 1 | SHOWROOM FLOORS |
| Typical floor | 66.26 | 15 | SHOWROOM FLOORS |
| Typical floor | 76.12 | 15 | SHOWROOM FLOORS |
| Typical floor | 72.12 | 6 | SHOWROOM FLOORS |
| Typical floor | 76.86 | 3 | SHOWROOM FLOORS |
| Lower ground floor | 56.97 | 3 | SHOWROOM FLOORS |
| Lower ground floor | 132.62 | 1 | SHOWROOM FLOORS |
| Typical floor | 134.57 | 3 | SHOWROOM FLOORS |
| Typical floor | 64.03 | 6 | SHOWROOM FLOORS |
| Upper ground floor | 66.26 | 2 | SHOWROOM FLOORS |
| Upper ground floor | 64.03 | 2 | SHOWROOM FLOORS |
| Upper ground floor | 62.83 | 2 | SHOWROOM FLOORS |
| Upper ground floor | 115.52 | 1 | SHOWROOM FLOORS |
| Lower ground floor | 115.52 | 1 | SHOWROOM FLOORS |
| Lower ground floor | 62.83 | 2 | SHOWROOM FLOORS |
| Lower ground floor | 67.37 | 1 | SHOWROOM FLOORS |
| Lower ground floor | 66.91 | 5 | SHOWROOM FLOORS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-12-08 | |
|---|---|---|
| Proposed completion | 2023-06-30 |
Quarterly progress
| 2021-Q1 | 2021-07-07 |
| 2021-Q2 | 2021-07-11 |
| 2021-Q3 | 2021-11-28 |
| 2021-Q4 | 2022-01-28 |
| 2022-Q1 | 2022-05-31 |
| 2022-Q3 | 2022-10-14 |
| 2022-Q4 | 2023-01-16 |
| 2023-Q1 | 2023-04-13 |
| 2023-Q2 | 2023-07-15 |
| 2023-Q3 | 2023-10-19 |
| 2023-Q4 | 2024-03-14 |
| 2024-Q1 | 2024-06-26 |
| 2024-Q2 | 2024-11-10 |
| 2024-Q3 | 2024-11-17 |
| 2025-Q1 | 2025-05-18 |
| 2024-Q4 | 2025-05-18 |
| 2025-Q2 | 2025-08-13 |
| 2025-Q3 | 2026-09-05 |
| 2025-Q4 | 2026-09-06 |
| 2026-Q1 | 2026-09-06 |
| 2026-Q2 | 2026-09-06 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAYA BUILDERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Bank of Maharashtra | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11093&inPromoter_ID=1916&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2017-06-21
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2019-11-25
- Building Permit Issue from Municipal Authority · 2019-12-02 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License as Promoter from competent Authority · 2019-11-15
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-09-17
- Other Document (ISSU OF LICENCE COMMERCIAL) · 2020-01-24
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2017-06-21
- CLU Certificate
- License as Promoter from competent Authority · 2019-11-15
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-09-17
- Other Document (ISSU OF LICENCE COMMERCIAL) · 2020-01-24
- 2021-Q1 · 2021-07-07
- 2021-Q2 · 2021-07-11
- 2021-Q3 · 2021-11-28
- 2021-Q4 · 2022-01-28
- 2022-Q1 · 2022-05-31
- 2022-Q3 · 2022-10-14
- 2022-Q4 · 2023-01-16
- 2023-Q1 · 2023-04-13
- 2023-Q2 · 2023-07-15
- 2023-Q3 · 2023-10-19
- 2023-Q4 · 2024-03-14
- 2024-Q1 · 2024-06-26
- 2024-Q2 · 2024-11-10
- 2024-Q3 · 2024-11-17
- 2025-Q1 · 2025-05-18
- 2024-Q4 · 2025-05-18
- 2025-Q2 · 2025-08-13
- 2025-Q3 · 2026-09-05
- 2025-Q4 · 2026-09-06
- 2026-Q1 · 2026-09-06
- 2026-Q2 · 2026-09-06