Overview
Green Lotus Utsav
MAYA ESTATE · Sahibzada Ajit Singh Nagar (Mohali)
Units842
Booked578 of 842As of 2026-06-30
Completion2023-12-31Proposed
Registered on2019-02-26
Valid to2025-06-30
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details · 27 unit types |
| Construction & progress | 2 progress details · 26 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 187 documents · 38 source links |
Registration
Registration
| Promoter | MAYA ESTATE | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0425 | |
| Registered on | 2019-02-26 | |
| Valid to | 2025-06-30 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2018-11-11 |
| CLU Certificate | |
| Defense Clearance | 2018-09-11 |
| Environment Clearance certificate/ NOC | 2018-10-12 |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2018-11-12 |
| Other Document (Noc Waste And Garbage) | 2018-10-11 |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹80,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 49,575.61 | |
|---|---|---|
| Towers | 18 | |
| Maximum floors | 33 | |
| Units | 842 | |
| Booked | 578 | |
| Booked as of | 2026-06-30 |
Unit types
| SHOP | 32.51 | 33 | 33 | SHOP |
| 3 BHK | 103.11 | 53 | 53 | TOWER-A |
| 3BHK | 103.11 | 53 | 52 | TOWER-B |
| 3BHK | 103.11 | 53 | 52 | TOWER-C |
| 3 BHK | 103.11 | 49 | 20 | TOWER-D |
| 3 BHK PENTHOUSE | 134.05 | 2 | 2 | TOWER-D |
| 3+S BHK | 125.04 | 53 | 52 | TOWER-E |
| 3+S BHK | 125.04 | 53 | 46 | TOWER-F |
| 3+S BHK | 125.04 | 53 | 34 | TOWER-G |
| 5+S BHK | 207.45 | 26 | 18 | TOWER-H |
| 5+S BHK | 207.45 | 26 | 8 | TOWER-I |
| 5BHK + DUPLEX | 308.71 | 18 | 9 | TOWER-J |
| 6 BHK DUPLEX | 470.36 | 1 | 0 | TOWER-J |
| 5 BHK LARGE | 332.59 | 4 | 2 | TOWER-J |
| 5 BHK LARGE PENTHOUSE | 378.01 | 2 | 0 | TOWER-J |
| 4BHK | 161.74 | 53 | 0 | TOWER-K |
| 4 BHK | 161.74 | 53 | 24 | TOWER-L |
| 4 BHK PENTHOUSE | 203.92 | 2 | 2 | TOWER-M |
| 4 BHK | 161.74 | 51 | 47 | TOWER-M |
| 3 BHK | 103.12 | 49 | 41 | TOWER-N |
| 3 BHK PENTHOUSE | 134.05 | 2 | 2 | TOWER-N |
| 3 BHK | 103.12 | 49 | 25 | TOWER-O |
| 3 BHK PENTHOUSE | 134.05 | 2 | 0 | TOWER-O |
| 3 BHK | 103.12 | 49 | 32 | TOWER-P |
| 3 BHK PENTHOUSE | 134.05 | 2 | 2 | TOWER-P |
| 3 BHK | 103.12 | 49 | 22 | TOWER-Q |
| 3 BHK PENTHOUSE | 134.05 | 2 | 0 | TOWER-Q |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-01-01 | |
|---|---|---|
| Proposed completion | 2023-12-31 |
Quarterly progress
| 2021-Q1 | 2021-07-22 | ||
| 2021-Q2 | 2021-08-07 | ||
| 2021-Q3 | 2021-10-24 | ||
| 2021-Q4 | 2022-01-15 | ||
| 2020-Q1 | 2022-01-30 | ||
| 2020-Q2 | 2022-01-30 | ||
| 2020-Q3 | 2022-01-30 | ||
| 2020-Q4 | 2022-01-30 | ||
| 2022-Q1 | 2022-04-21 | ||
| 2022-Q2 | 2022-08-02 | ||
| 2022-Q3 | 2022-10-09 | ||
| 2022-Q4 | 2023-01-08 | ||
| 2023-Q1 | 2023-04-13 | ||
| 2023-Q2 | 2023-07-15 | ||
| 2023-Q3 | 2023-10-19 | ||
| 2023-Q4 | 2024-03-14 | ||
| 2024-Q1 | 2024-06-17 | ||
| 2024-Q2 | 2024-08-30 | ||
| 2024-Q3 | 2024-11-09 | ||
| 2024-Q4 | 2025-04-04 | ||
| 2025-Q1 | 2025-04-04 | ||
| 2025-Q2 | 2025-08-13 | ||
| 2025-Q3 | 2026-09-07 | ||
| 2025-Q4 | 2026-09-07 | ||
| 2026-Q1 | 2026-09-07 | ||
| 2026-Q2 | 2026-09-07 | 0 | 0 |
Extensions
| Valid to |
|---|
| 2025-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAYA ESTATE | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=10610&inPromoter_ID=1493&inPromoterType=10610&inQUProject_ID=5000&inQUProject_DN=QUP2026S20265000&inQUProjectYear=2026&inQUProjectQTR=SecondQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10610&inPromoter_ID=1493&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-11-11
- Borewell Registration certificate from Central Ground Water Authority · 2018-10-11
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Defense Clearance · 2018-09-11
- Environment Clearance certificate/ NOC · 2018-10-12
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-11-12
- Other Document (Forest N O C) · 2018-08-13 · Sign in to download
- Other Document (Noc Waste And Garbage) · 2018-10-11
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-11-11
- CLU Certificate
- Defense Clearance · 2018-09-11
- Environment Clearance certificate/ NOC · 2018-10-12
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-11-12
- Other Document (Noc Waste And Garbage) · 2018-10-11
- Consent details of actual owner of Land
- Extension order · Sign in to download
- 2021-Q1 · 2021-07-22
- 2021-Q2 · 2021-08-07
- 2021-Q3 · 2021-10-24
- 2021-Q4 · 2022-01-15
- 2020-Q1 · 2022-01-30
- 2020-Q2 · 2022-01-30
- 2020-Q3 · 2022-01-30
- 2020-Q4 · 2022-01-30
- 2022-Q1 · 2022-04-21
- 2022-Q2 · 2022-08-02
- 2022-Q3 · 2022-10-09
- 2022-Q4 · 2023-01-08
- 2023-Q1 · 2023-04-13
- 2023-Q2 · 2023-07-15
- 2023-Q3 · 2023-10-19
- 2023-Q4 · 2024-03-14
- 2024-Q1 · 2024-06-17
- 2024-Q2 · 2024-08-30
- 2024-Q3 · 2024-11-09
- 2024-Q4 · 2025-04-04
- 2025-Q1 · 2025-04-04
- 2025-Q2 · 2025-08-13
- 2025-Q3 · 2026-09-07
- 2025-Q4 · 2026-09-07
- 2026-Q1 · 2026-09-07