Overview
GREEN VILLE
AYANSH VENTURES (OPC) PRIVATE LIMITED · RAIGARH
Units93
Booked40 of 93As of 2025-03-31
Construction progress21%As of 2025-03-31
Completion2027-10-05Revised · Proposed 2027-06-05
Registered on2022-06-10
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 2 cost heads · 9 quarters |
| Technical report | |
| Site & area | 3 site details · 93 unit types |
| Construction & progress | 4 progress details · 9 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 66 documents · 7 source links |
Registration
Registration
| Promoter | AYANSH VENTURES (OPC) PRIVATE LIMITED | |
|---|---|---|
| District | RAIGARH | |
| Regulator | CG RERA | |
| Registration number | PCGRERA100622001436 | |
| Registered on | 2022-06-10 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2027-06-05 | |
| Revised completion | 2027-10-05 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹19,73,24,000 | |
|---|---|---|
| Construction | ₹24,31,19,000 |
Quarterly money flows
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹0 |
| 2022-Q4 | ₹0 |
| 2023-Q1 | ₹10,917.5 |
| 2023-Q2 | ₹1,27,812.71 |
| 2023-Q3 | ₹1,92,101.2 |
| 2023-Q4 | ₹15,64,789.98 |
| 2024-Q4 | ₹22,210 |
| 2025-Q1 | ₹17,908 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 93 | |
|---|---|---|
| Booked | 40 | |
| Booked as of | 2025-03-31 |
Unit types
| Plot-92 | 1 | 0 |
| A-1 | 1 | 1 |
| A-2 | 1 | 1 |
| A-3 | 1 | 1 |
| A-4 | 1 | 1 |
| A-5 | 1 | 0 |
| A-6 | 1 | 0 |
| A-7 | 1 | 0 |
| A-8 | 1 | 0 |
| B-1 | 1 | 1 |
| B-2 | 1 | 0 |
| B-3 | 1 | 0 |
| B-4 | 1 | 0 |
| B-5 | 1 | 0 |
| B-6 | 1 | 0 |
| B-7 | 1 | 0 |
| B-8 | 1 | 0 |
| C-1 | 1 | 1 |
| C-2 | 1 | 1 |
| C-3 | 1 | 1 |
| C-4 | 1 | 0 |
| C-5 | 1 | 0 |
| C-6 | 1 | 0 |
| C-7 | 1 | 0 |
| D-1 | 1 | 1 |
| D-2 | 1 | 0 |
| D-3 | 1 | 0 |
| D-4 | 1 | 0 |
| D-5 | 1 | 1 |
| D-6 | 1 | 0 |
| D-7 | 1 | 0 |
| E-1 | 1 | 0 |
| E-2 | 1 | 0 |
| E-3 | 1 | 0 |
| E-4 | 1 | 1 |
| F-1 | 1 | 0 |
| F-2 | 1 | 1 |
| F-3 | 1 | 0 |
| F-4 | 1 | 0 |
| F-5 | 1 | 0 |
| F-6 | 1 | 0 |
| F-7 | 1 | 0 |
| F-8 | 1 | 0 |
| F-9 | 1 | 0 |
| F-10 | 1 | 0 |
| F-11 | 1 | 0 |
| G-1 | 1 | 1 |
| G-2 | 1 | 1 |
| G-3 | 1 | 1 |
| G-4 | 1 | 1 |
| G-5 | 1 | 1 |
| G-6 | 1 | 1 |
| G-7 | 1 | 1 |
| G-8 | 1 | 1 |
| G-9 | 1 | 1 |
| G-10 | 1 | 1 |
| G-11 | 1 | 1 |
| H-1 | 1 | 1 |
| H-2 | 1 | 1 |
| H-3 | 1 | 1 |
| H-4 | 1 | 1 |
| H-5 | 1 | 1 |
| H-6 | 1 | 1 |
| H-7 | 1 | 1 |
| H-8 | 1 | 1 |
| H-9 | 1 | 1 |
| H-10 | 1 | 1 |
| H-11 | 1 | 0 |
| I-1 | 1 | 0 |
| I-2 | 1 | 0 |
| I-3 | 1 | 0 |
| I-4 | 1 | 0 |
| I-5 | 1 | 0 |
| I-6 | 1 | 0 |
| I-7 | 1 | 0 |
| I-8 | 1 | 0 |
| I-9 | 1 | 0 |
| I-10 | 1 | 0 |
| I-11 | 1 | 0 |
| I-12 | 1 | 0 |
| J-1 | 1 | 1 |
| J-2 | 1 | 0 |
| J-3 | 1 | 1 |
| J-4 | 1 | 1 |
| J-5 | 1 | 0 |
| J-6 | 1 | 1 |
| J-7 | 1 | 1 |
| J-8 | 1 | 1 |
| J-9 | 1 | 0 |
| J-10 | 1 | 0 |
| J-11 | 1 | 0 |
| J-12 | 1 | 0 |
| J-13 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 21% | |
|---|---|---|
| As of | 2025-03-31 | |
| Proposed completion | 2027-06-05 | |
| Revised completion | 2027-10-05 |
Quarterly progress
| 2022-Q2 | 0% |
| 2022-Q3 | 9% |
| 2022-Q4 | 9% |
| 2023-Q1 | 11% |
| 2023-Q2 | 13% |
| 2023-Q3 | 15% |
| 2023-Q4 | 17% |
| 2024-Q4 | 20% |
| 2025-Q1 | 21% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AYANSH VENTURES (OPC) PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTc2MA==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities