DOSLJaipur, Rajasthan Workspace

Overview

GULAB HARI ENCLAVE-B

DILIP SINGH · Jaipur
Units66
Booked33 of 66As of 2025-06-30
Completion2026-07-31Revised · Proposed 2023-10-17
Registered on2023-12-05
Valid to2026-07-31

Sections

Property title & search report
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area6 site details · 23 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details
The evidence
Sources41 documents · 6 source links

Registration

Registration

PromoterDILIP SINGH
DistrictJaipur
RegulatorRajasthan RERA
Registration numberRAJ/P/2023/2845
Registered on2023-12-05
Valid to2026-07-31
Project typePlotted
Status (as filed)COMPLETED
Proposed completion2023-10-17
Revised completion2026-07-31