DOSLJaipur, Rajasthan Workspace

Overview

Gulmohar Gardens Phase V

Ashiana Manglam Builders · Tonk Road
Units65
Booked0 of 65As of 2018-03-31
Completion2018-11-30Revised · Proposed 2015-10-01
Registered on2017-08-17
Valid to2018-11-30

Sections

Property title & search report
Approvals1 occupancy certificate
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area6 site details · 47 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details
The evidence
Sources243 documents · 6 source links

Registration

Registration

PromoterAshiana Manglam Builders
DistrictJaipur
LocalityTonk Road
RegulatorRajasthan RERA
Registration numberRAJ/P/2017/057
Registered on2017-08-17
Valid to2018-11-30
Project typeGroup Housing
Status (as filed)COMPLETED & OC ISSUED
Proposed completion2015-10-01
Revised completion2018-11-30