Overview
Gulnaar Zenium
Gul-E-Punjab developers LLP · Sahibzada Ajit Singh Nagar (Mohali)
Units104
Completion2029-05-31Proposed
Valid to2029-05-31
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 3 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 24 source links |
Registration
Registration
| Promoter | Gul-E-Punjab developers LLP | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR1053 | |
| Valid to | 2029-05-31 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-05-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2023-07-19 | |
| CLU Certificate | ||
| Electric Substation NOC | 2024-05-14 | |
| License as Promoter from competent Authority | 2023-07-20 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2023-12-20 | |
| NOC from NHAI/ PWD | 2024-01-17 | |
| Other Document (Affidavit for NOCs) | Legal Documents (Received) | 2024-05-30 |
| Other Document (DRAINAGE NOC) | 2023-12-19 | |
| Other Document (FOREST NOC) | 2023-10-17 | |
| Other Document (TREATED WASTE WATER NOC) | 2023-12-12 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-02-21 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,21,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 14,765.364 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 78 | |
| Units | 104 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Shops | 32.035 | 4 | COMMERCIAL |
| Flat No 101 to 126, 201 to 226, 301 to 326 | 205.981 | 78 | UNIT 1 - TOWER A TO C 4 BHK PLUS SERVANT |
| Flat No 403 to 413, 503 to 513 | 205.981 | 22 | UNIT 2 - TOWER D AND E - 4 BHK PLUS SERVANT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-06-21 | |
|---|---|---|
| Proposed completion | 2029-05-31 |
Quarterly progress
| 2024-Q3 | 2024-12-16 |
| 2024-Q4 | 2025-10-25 |
| 2025-Q1 | 2025-10-25 |
| 2025-Q2 | 2025-10-25 |
| 2025-Q3 | 2025-10-25 |
| 2025-Q4 | 2026-01-14 |
| 2026-Q1 | 2026-04-13 |
| 2026-Q2 | 2026-07-26 |
| 2026-Q3 | 2026-10-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Gul-E-Punjab developers LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12017&inPromoter_ID=2903&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2023-07-19
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-05-14
- License as Promoter from competent Authority · 2023-07-20
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-12-20
- NOC from NHAI/ PWD · 2024-01-17
- Other Document (Board Resolution) · 2024-05-07 · Sign in to download
- Other Document (DRAINAGE NOC) · 2023-12-19
- Other Document (FOREST NOC) · 2023-10-17
- Other Document (Solid waste and Construction and Demolation waste) · 2023-12-12 · Sign in to download
- Other Document (TREATED WASTE WATER NOC) · 2023-12-12
- Pollution Clearance from Punjab Pollution Control Board · 2024-02-21
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2023-07-19
- CLU Certificate
- Electric Substation NOC · 2024-05-14
- License as Promoter from competent Authority · 2023-07-20
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-12-20
- NOC from NHAI/ PWD · 2024-01-17
- Other Document (Affidavit for NOCs) · 2024-05-30
- Other Document (DRAINAGE NOC) · 2023-12-19
- Other Document (FOREST NOC) · 2023-10-17
- Other Document (TREATED WASTE WATER NOC) · 2023-12-12
- Pollution Clearance from Punjab Pollution Control Board · 2024-02-21
- 2024-Q3 · 2024-12-16
- 2024-Q4 · 2025-10-25
- 2025-Q1 · 2025-10-25
- 2025-Q2 · 2025-10-25
- 2025-Q3 · 2025-10-25
- 2025-Q4 · 2026-01-14
- 2026-Q1 · 2026-04-13
- 2026-Q2 · 2026-07-26
- 2026-Q3 · 2026-10-13