Overview
GURGAON INTERNATIONAL CITY
M3M INDIA INFRASTRUCTURES PRIVATE LIMITED · Gurugram
Units291
Completion2034-09-30Proposed
Registered on2025-10-16
Valid to2034-09-30
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 137 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 32 documents · 2 source links |
Registration
Registration
| Promoter | M3M INDIA INFRASTRUCTURES PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/991/723/2025/94 DATED 16.10.2025 | |
| Registered on | 2025-10-16 | |
| Valid to | 2034-09-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2034-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | DTCP Licence no 168 of 2025 dated 08.09.2025 valid till 07.09.2025 | Town & Country Planning Department | |
| Layout Plan | 2025-09-08 | ||
| Building Plan | 2015-01-01 | ||
| I. LICENCE | 2025-09-08 | ||
| II. EP APPROVAL | 2025-09-01 | ||
| III. FOREST NOC | 2025-05-24 | ||
| IV. ASSURANCE STP TREATED WATER | 2025-09-12 | ||
| V. ASSURANCE DRINKING WATHR | 2025-09-12 | ||
| VI. ASSURANCE SEWERAGE CONNECTION | 2025-09-12 | ||
| VII. ASSURANCE STORM WATER | 2025-09-12 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,99,81,76,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹12,34,64,35,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1 | |
|---|---|---|
| Units | 291 |
Unit types
| Plot | 9 | |
| Plot | 14 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 19 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 29 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 16 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 4 | |
| Plot | 6 | |
| Plot | 1 | |
| Plot | 12 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 3 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 4 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 46 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-10-01 | |
|---|---|---|
| Proposed completion | 2034-09-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M3M INDIA INFRASTRUCTURES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | KOTAK MAHINDRA BANK | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/3699
- Registration Certificate · 2025-10-16
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2025-09-16 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2025-09-16
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2025-09-16
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2025-09-16 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2025-09-16
- LC IV AND BILLATERALS · 2025-10-14 · Sign in to download
- INFORMATION TO REVENUE DEPARTMENT · 2025-10-14 · Sign in to download
- ZONING PLAN · 2025-10-14
- JAMABANDI · 2025-10-14 · Sign in to download
- ASSURANCE FOR SEWERAGE · 2025-10-14 · Sign in to download
- CA CERTIFICATE OF INVENTORY · 2025-10-14 · Sign in to download
- SHAJRA · 2025-10-14 · Sign in to download
- CA CERTIFICATE NET WORTH · 2025-10-14 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2025-10-14 · Sign in to download
- ASSURANCE- STP TREATED WATER · 2025-10-14 · Sign in to download
- EP APPROVAL · 2025-10-14
- CA CERTIFICATE OF NON DEFAULT · 2025-10-14 · Sign in to download
- CA CERTIFICATE INCURRED · 2025-10-14 · Sign in to download
- LICENCE · 2025-10-14
- LOI · 2025-10-14 · Sign in to download
- APPLICATION OF SERVICE PLAN ESTIMATE · 2025-10-14
- ASSURANCE- STORM WATER DRAINAGE · 2025-10-14 · Sign in to download
- ASSURANCE- WATER SUPPLY DRINKING WATER · 2025-10-14 · Sign in to download
- CASHFLOW STATEMENT · 2025-10-14 · Sign in to download
- LAYOUT PLAN · 2025-10-14
- MUTATION · 2025-10-14 · Sign in to download
- REP-II · 2025-10-14 · Sign in to download
- ALLOTMENT LETTER · 2025-11-04 · Sign in to download
- APPLICATION FORM · 2025-11-04 · Sign in to download
- BUILDER BUYER AGREEMENT · 2025-11-04 · Sign in to download
- CONVEYANCE DEED · 2025-11-04 · Sign in to download