Overview
H 138 GOVERDHAN VIHAR
JANAK NANDINI REALTORS PRIVATE LIMITED · NAHARYA KA BAS
Units64
Booked0 of 64As of 2022-03-31
Completion2020-02-29Revised · Proposed 2015-02-10
Registered on2017-11-17
Valid to2022-02-28
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 7 site details · 1 unit type |
| Construction & progress | 3 progress details · 1 quarter · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 15 documents · 8 source links |
Registration
Registration
| Promoter | JANAK NANDINI REALTORS PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Locality | NAHARYA KA BAS | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2017/445 | |
| Registered on | 2017-11-17 | |
| Valid to | 2022-02-28 | |
| Project type | Group Housing | |
| Status (as filed) | LAPSED | |
| Proposed completion | 2015-02-10 | |
| Revised completion | 2020-02-29 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | LAPSED | |
|---|---|---|
| Valid to | 2022-02-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹70,01,960 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹6,46,17,402.2 |
Quarterly money flows
| Quarter | Escrow balance |
|---|---|
| 2022-Q1 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,083.47 | |
|---|---|---|
| Built-up (m²) | 3,569.73 | |
| Towers | 1 | |
| Maximum floors | 9 | |
| Units | 64 | |
| Booked | 0 | |
| Booked as of | 2022-03-31 |
Unit types
| Type | Carpet (m²) | Units | Booked | Tower |
|---|---|---|---|---|
| RESIDENTIAL | 1,757.28 | 64 | 0 | H 138 GOVERDHAN VIHAR |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 1900-01-01 | |
|---|---|---|
| Proposed completion | 2015-02-10 | |
| Revised completion | 2020-02-29 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2022-Q1 | 2022-04-25 | 0 |
Extensions
| Valid to |
|---|
| 2021-02-28 |
| 2022-02-28 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | JANAK NANDINI REALTORS PRIVATE LIMITED | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 2 |
Professional firms
| Role | Firm |
|---|---|
| Contractor | Anand Constructions |
| Engineer | Prime Tech Design Consultants |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=TM1TcnJKX8--Gb95YhVelA
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/TM1TcnJKX8--Gb95YhVelA
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=TM1TcnJKX8%2B%2BGb95YhVelA%3D%3D&QuarterIdEnc=1K19NjpnOLGvL3EWAklMNw%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=MbmhUpSktJ8%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Copy Of Approved Site Plan
- NOC for fire
- NOC from Airport Authority of India
- Project Related Approval Documents (Other than Plotted)
- FormFUploadedPathString · Sign in to download
- FormFUploadedPathString · Sign in to download
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2022-03-31 · Sign in to download
- R2_UploadDoc · 2022-03-31 · Sign in to download
- R3_UploadedPath · 2022-04-21 · Sign in to download
- Extension order · Sign in to download
- Extension order · Sign in to download