Overview
HAPPY MART
HIRNOT GROUP · Ghaziabad
Units129
Completion2028-04-12Proposed
Registered on2023-07-07
Valid to2028-04-12
Approvals1
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 20 unit types |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 52 documents · 21 source links |
Registration
Registration
| Promoter | HIRNOT GROUP | |
|---|---|---|
| District | Ghaziabad | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ324723 | |
| Registered on | 2023-07-07 | |
| Valid to | 2028-04-12 | |
| Project type | Commercial | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2028-04-12 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | GDA/BP/22-23/1020 | 2023-04-13 | 2028-04-12 | Ghaziabad Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹17,50,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,895 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 4 | |
| Units | 129 |
Unit types
| SHOP | 13.97 | 4 | HAPPY MART | GF |
| SHOP | 14.17 | 2 | HAPPY MART | GF |
| SHOP | 14.72 | 8 | HAPPY MART | GF |
| SHOP | 14.98 | 24 | HAPPY MART | 1 |
| SHOP | 13.94 | 4 | HAPPY MART | 1 |
| SHOP | 14.69 | 2 | HAPPY MART | 1 |
| SHOP | 9.55 | 2 | HAPPY MART | 1 |
| SHOP | 14.98 | 24 | HAPPY MART | 2 |
| SHOP | 13.94 | 4 | HAPPY MART | 2 |
| SHOP | 14.69 | 2 | HAPPY MART | 2 |
| SHOP | 9.55 | 2 | HAPPY MART | 2 |
| STUDIO | 18.97 | 21 | HAPPY MART | 3 |
| STUDIO | 19.77 | 1 | HAPPY MART | 3 |
| STUDIO | 28.15 | 2 | HAPPY MART | 3 |
| STUDIO | 18.38 | 2 | HAPPY MART | 3 |
| STUDIO | 16.76 | 2 | HAPPY MART | 3 |
| STUDIO | 16.46 | 1 | HAPPY MART | 3 |
| STUDIO | 18.25 | 2 | HAPPY MART | 3 |
| STUDIO | 18.97 | 19 | HAPPY MART | 4 |
| STUDIO | 19.77 | 1 | HAPPY MART | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-05-22 | |
|---|---|---|
| Proposed completion | 2028-04-12 |
Quarterly progress
| 2023-Q2 | |
| 2023-Q3 | |
| 2023-Q4 | |
| 2024-Q1 | |
| 2024-Q2 | |
| 2024-Q3 | |
| 2024-Q4 | |
| 2025-Q1 | |
| 2025-Q2 | |
| 2025-Q3 | 58.04% |
| 2025-Q4 | 58.23% |
| 2026-Q1 | 58.32% |
| 2026-Q2 | 64.93% |
| 2026-Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HIRNOT GROUP | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=+JtatipbizQ=&hfFlag=q5Tk0QUeJB8oatkp/Oqbxw==&NPJ6RAme=feXv6rgl/3BXe0hInoOb5w==&PaURJEMAN4=ZL9MNERkNdairbujQsLghg==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GHAZIABAD
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=%2BJtatipbizQ=
- Commencement Certificate · 2023-05-25
- Other Plan(If Any) · 2023-05-25
- Waste Disposal Plan · 2023-06-04
- Water Supply Plan · 2023-06-04
- Electricity Supply Plan · 2023-06-04
- Development Work Plan · 2023-06-04
- CA CERTIFICATE · 2023-05-25 · Sign in to download
- ARCHITECT CERTIFICATE · 2023-05-25 · Sign in to download
- ENGINEERS CERTIFICATE · 2023-05-25 · Sign in to download
- Other · 2023-07-06 · Sign in to download
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- 2023-Q2
- 2023-Q3
- 2023-Q4
- 2024-Q1
- 2024-Q2
- 2024-Q3
- 2024-Q4
- 2025-Q1
- 2025-Q2
- 2025-Q3
- 2025-Q4
- 2026-Q1
- 2026-Q2
- 2026-Q3