Building plan (BDA)Sanctioned 11 Feb 2026No. BDA/NM/AS/AA-5/TS-4/E/69/2025-26
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted, 9 of 9 parcelsDates and authorities below
Permits
Approval letters
Building plan (BDA)
Sanctioned 11 Feb 2026 · No. BDA/NM/AS/AA-5/TS-4/E/69/2025-26
Power NOC
Filed with the registration
Fire department
Disputes & cases
Are there court cases or buyer complaints on this project?
Clear1 clear
Builder: Unknown promoter
Court cases on the project's land
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Court cases against the builder and landowners
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
None found.
Buyer complaints filed with K-RERA on this project
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None found.
Buyer complaints on other projects by this builder
0 cases
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
Search pending.
Court records searched by the builder's and the project's names on 5 Nov 2026: 35 cases returned, 0 name this project's promoter company or this project. The rest name other parties and are left out.
✓Confirmed: the record names this project, its land or its promoter company?Likely: matched by the builder's nameHigh: a court stay or a pending case on the filed landMedium: open, or the record does not sayLow: decided or closed
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Unit mix filed
Villas · avg 98 m² 100%
Unit types
Location & risks
What is the location like?
Groundwater, taluk average21.3 m below groundAnekal taluk, July 2023
Water supply, as filedOtherDeclared by the promoter
Metro, operationalabout 9 kmNallur Halli
Construction & progress
How is it being built, and when will it be ready?
CompletionFirst return due
Progress
Completion, architect
Registered: its first quarterly return is still to come
Work left
By component
Registered: its first quarterly return is still to come
Quarterly return
Registered: its first quarterly return is still to come
Dates
Dates
Developer
Can the developer deliver?
SoldFirst return due
Sold in the latest quarterFirst return due
Funding
Estimated cost
Land · ₹7.18 Cr 4.8%Development · ₹142.30 Cr 95.2%
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan (BDA)
Sanctioned 11 Feb 2026
Escrow bank
ICICI Bank · MG Road, Bengaluru
Stage
Certified progress
Registered: its first quarterly return is still to come
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Data room
Documents filed for this project
Documents filed179On K-RERA
Available16492% of filed
K-RERA only15
Approvals with a validity dateNone read
Approvals & NOCs
Available
Available
Available
Available
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
K-RERA only
Filed 22 Jul 2026Available
Filed 22 Jul 2026Available
Filed 22 Jul 2026Available
Source: K-RERA project page and the documents filed there, as read by us. 6 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Harmony Homes in the interactive atlas
12 Feb 2025DC
No sale deed
25 Nov 2025E Khatha · Neriga Panchayath
5 Gunta
87/24
1 Feb 2025DC
5 Mar 2022
25 Nov 2025E Khatha · Neriga Panchayath
10 Gunta
87/25, 87/26, 87/27
1 Feb 2025DC
1 Jul 2011
25 Nov 2025E Khatha · Neriga Panchayath
11 Gunta + 10 Gunta + 11 Gunta
87/33
1 Feb 2025DC
10 Jan 2023
25 Nov 2025E Khatha · Neriga Panchayath
1 Acre 1 Gunta
87/34
21 Mar 2025DC
3 Apr 2024
25 Nov 2025E Khatha · Neriga Panchayath
2 Acre 23 Gunta
87/35
12 Feb 2025DC
No sale deed
25 Nov 2025E Khatha · Neriga Panchayath
1 Acre 29 Gunta
K-RERA filing, land schedule
The whole project
Approval or registration
Building plan sanctioned
BDA · plan BDA/NM/AS/AA-5/TS-4/E/69/2025-26
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/308/PR/290726/008856
K-RERA registration ·
Approval or registrationTransfer of the land
Read from the original documentDescribed in the filing or another document; the original is not read here
Title
Charges
Developer's project loan
None declared
Survey sketch
Survey sketch filed with K-RERA
Page 1
Page 1 of the survey sketch. Filed with K-RERA: ADLR Sketch.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
Survey plots, KGIS cadastral
Road, stream, tank or settlement (not a plot)
Approximate location: the filed pin, good to the neighbourhood, not the plot
Dated 1 Jul 2011, 5 Mar 2022, 10 Jan 2023 and 1 more
Not verified yet: Title opinion; Records searched to; Charges on the land; Landowner share of sales; Title report; Schedule in the EC vs KGIS neighbours; Encumbrance certificate, Form 15; Sketch, sanction and mutation vs KGIS map; Area on the KGIS map; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; East Bengaluru, past year; Bengaluru, past year; East Bengaluru since 2022; This project vs East Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields.
Power lines, drains and flood locations around the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Storm drain, smaller
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Registered: its first quarterly return is still to come
Sold per quarter
Registered: its first quarterly return is still to come
K-RERA inventory
Registered: its first quarterly return is still to come
Compliance
Escrow
Registered: its first quarterly return is still to come
Escrow and filings
Escrow bank
ICICI Bank · MG Road, Bengaluru
Not verified yet: Receivable, sold villas; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, smaller
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot
Anekal taluk average, July 2023: 21.3 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class
Through the year
January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several)
Water supply, as filed
Other
Distances
Within 3 km of the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Government-flagged flood location
Approximate location: the filed pin, good to the neighbourhood, not the plot