DOSLChhattisgarh Workspace

Overview

HARSH PRIDE (PHASE-II)

ABHISHEK BUILDCON · RAIPUR
Construction progress100%As of 2022-12-31
Completion2023-08-27Revised · Proposed 2020-03-31
Registered on2018-07-23
Approvals1

Sections

Property title & search report
Approvals1 approval
Contract & costs2 cost heads · 18 quarters
Technical report
Site & area4 unit types
Construction & progress4 progress details · 18 quarters
Developer & finance
Developer4 developer details
The evidence
Sources131 documents · 4 source links

Registration

Registration

PromoterABHISHEK BUILDCON
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA230718000630
Registered on2018-07-23
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2020-03-31
Revised completion2023-08-27