Overview
HARSHIT LANDMARK (PHASE-I, BLOCK -A&B)
SINGHANIA BUILDCON PRIVATE LIMITED · RAIPUR
Units160
Booked135 of 160As of 2021-09-30
Construction progress100%As of 2021-09-30
Completion2021-08-30Revised · Proposed 2020-11-30
Registered on2018-07-16
Approvals4
Cases3
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 3 cases |
| Contract & costs | 2 cost heads · 13 quarters |
| Technical report | |
| Site & area | 3 site details · 6 unit types |
| Construction & progress | 4 progress details · 13 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 86 documents · 11 source links |
Registration
Registration
| Promoter | SINGHANIA BUILDCON PRIVATE LIMITED | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA160718000539 | |
| Registered on | 2018-07-16 | |
| Project type | Mixed Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2020-11-30 | |
| Revised completion | 2021-08-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-PRO-2021-01287 | CG RERA | Complaint | Disposed | 2021-07-16 |
| M-PRO-2019-00694 | CG RERA | Complaint | Disposed | 2019-09-05 |
| M-PRO-2019-00257 | CG RERA | Complaint | Disposed | 2019-05-23 |
Complaints & cases
| Cases | 3 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹10,75,08,000 | |
|---|---|---|
| Construction | ₹19,77,49,000 |
Quarterly money flows
| 2018-Q3 | ₹9,965 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹0 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹1,887 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹1,11,973.52 |
| 2021-Q3 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 160 | |
|---|---|---|
| Booked | 135 | |
| Booked as of | 2021-09-30 |
Unit types
| Residential | 0 | 0 | |
| 2BHK | 41.85 | 80 | 69 |
| 3BHK | 58.91 | 80 | 66 |
| 1BHK | 0 | 0 | 0 |
| 1BHK | 0 | 0 | 0 |
| 1BHK | 0 | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2021-09-30 | |
| Proposed completion | 2020-11-30 | |
| Revised completion | 2021-08-30 |
Quarterly progress
| 2018-Q3 | 0% |
| 2018-Q4 | 50% |
| 2019-Q1 | 53% |
| 2019-Q2 | 57% |
| 2019-Q3 | 57% |
| 2019-Q4 | 60% |
| 2020-Q1 | 68% |
| 2020-Q2 | 68% |
| 2020-Q3 | 68% |
| 2020-Q4 | 74% |
| 2021-Q1 | 93% |
| 2021-Q2 | 93% |
| 2021-Q3 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SINGHANIA BUILDCON PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | DCB Bank | |
| Other projects in this city pack | 13 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NjIz
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Apartment Details · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Stilt Basement Parking · Sign in to download
- Open Parking · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Audit Report
- CA Certificate
- Engg Certificate
- Architect Certificate
- Audit Report
- CA Certificate
- Engg Certificate
- Architect Certificate
- Audit Report
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2021-07-16 · Sign in to download
- Final order · 2019-09-05 · Sign in to download
- Final order · 2019-05-23 · Sign in to download
- Approval Letter of Town And Country Planning
- Nazul clearance in case of Nazul Area
- Development Permission from competent authorities
- M-PRO-2021-01287 · Sign in to download
- M-PRO-2019-00694 · Sign in to download
- M-PRO-2019-00257 · Sign in to download