Overview
HEARTSONG PHASE 6
EXPERION DEVELOPERS PVT. LTD. · Gurugram
Completion2017-12-19Revised · Proposed 2017-12-19
Registered on2019-10-03
Valid to2020-05-13
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 3 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 19 documents · 3 source links |
Registration
Registration
| Promoter | EXPERION DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/360/92/2019/54 DATED 03.10.2019 | |
| Registered on | 2019-10-03 | |
| Valid to | 2020-05-13 | |
| Status (as filed) | Registered | |
| Proposed completion | 2017-12-19 | |
| Revised completion | 2017-12-19 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No 38 of 2010 | Town & Country Planning Department | |
| Layout Plan | 2012-09-18 | ||
| Building Plan | 2012-09-18 | ||
| I. LISENSE APPROVAL (LISENSE NO 38 OF 2010) | 2010-05-14 | ||
| II. BUILDING PLAN APPROVAL | 2012-09-18 | ||
| III. ENVIRONMENT CLEARANCE APPROVAL | 2012-10-08 | ||
| IV. AIRPORT HEIGHT CLEARANCE APPROVAL | 2012-01-27 | ||
| V. SERVICE PLAN ESTIMATE APPROVAL | 2013-04-04 | ||
| VI. FOREST NOC | 2012-05-08 | ||
| VII. OCCUPATION CERTIFICATE | 2017-12-19 | ||
| VIII. HUDA CONSTRUCTION WATER NOC | 2012-02-23 | ||
| IX. MINING APPROVAL | 2014-03-07 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,80,00,000 | |
|---|---|---|
| Construction | ₹20,96,00,000 | |
| Total | ₹29,60,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 175 |
|---|
Unit types
| Type | Units |
|---|---|
| 1 | 106 |
| 2 | 67 |
| 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2013-04-01 | |
|---|---|---|
| Proposed completion | 2017-12-19 | |
| Revised completion | 2017-12-19 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | EXPERION DEVELOPERS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | KOTAK MAHINDRA BANK | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/621
- https://nominatim.openstreetmap.org/search?q=sector+108%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2019-10-03
- SITE PLAN · 2019-09-05
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-05-04 · Sign in to download
- DEMARCATION PLAN · 2019-05-04
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-05-04 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-05-04
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-05-04
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-05-07
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-05-06 · Sign in to download
- GIST OF AGREEMENT · 2019-05-07 · Sign in to download
- DRAFT AGGREMENT · 2019-05-07 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-05-06 · Sign in to download
- ZONING PLAN · 2019-05-06
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-05-06
- DRAFT ALLOTMENT LETTER · 2019-05-07 · Sign in to download
- BALANCE SHEETS · 2019-05-07 · Sign in to download
- NO DEBT CERTIFICATE · 2019-05-07 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download